Public / civic · Co. Galway
Loughrea Farranalynch & Baunoge, St. Raphael’s College, Co. Galway
Granted 8 Aug 2025 (final grant issued 16 Sep 2025)
Key facts
- Planning application 2560781 at Loughrea Farranalynch & Baunoge, St. Raphael’s College, Co. Galway: Two storey school building.
- It was received by Galway County Council on 17 Jun 2025.
- Status: Granted 8 Aug 2025 (final grant issued 16 Sep 2025).
- Work started on site on 31 Mar 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Galway County Council planning register, checked 2 Jun 2026. Open the council's file
Since you last looked
Worked out in this browser from the record's own dates.
What and where
Two storey school building
for a two storey school building, consisting of classrooms, SEN classroom, technology room and all associated rooms with a gross floor area of 422 m², as well as an external store (gross floor area of 50 m²), with external secure play area and all associated site works. This development is within the curtilage of protected structures RPS 321,322 & 3495
Description as published by the council. Its text starts part-way through a sentence.
- Location
- St. Raphael’s College, Co. Galway Map
- Council
- Galway County Council
- Planning reference
- 2560781
Numbers and dates
- Floor area
- 472 m²
- Project type
- Public / civic
- Received
- 17 Jun 2025
- Decision to grant
- 8 Aug 2025
- Final grant
- 16 Sep 2025
- Site start
- 31 Mar 2026
- Protected structure
- Yes, RPS 321
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2560781 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Galway County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Site starts
Commencement notices for this permission
- 31 Mar 2026Work started · phase 1 · Construction of two storey school building and all ancillary site development works
- 15 Jul 2026Work started · phase 2 · Construction of external store and all ancillary site development works
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.