Save this project to account
Connected projectGranted

2 dwellings, No. 2 Dalysfort Road, Salthill, Galway

Granted · No. 2 Dalysfort Road, Salthill, Galway

Planning units2Source-stated
Planning floor area230.39 m²Source-stated; verify
Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

Permission for development which consists of permission for retention is sought for partially constructed dwelling (previously granted planning permission under planning application Ref. No 23/63), covered barbecue area building, rear garden landscaping, minor alterations to elevations of partially constructed dwelling and all associated works and services on revised site boundaries. Permission is also sought to complete construction of the dwelling, covered barbecue area building, rear garden landscaping and all associated works and services on revised site boundaries

Planning authority
Galway City Council
Lead planning reference
2660022
Application date
30 Jan 2026
Decision date
26 Mar 2026
Project type
Small residential
Value band
€500k–1m
Public agent
Ruairc O Tuairisg

Exact evidence

Planning records

2660022 · Planning application

Galway City Council · CONDITIONAL · 2026-03-26

2 units · Source-stated planning-record quantity

230.39 m² · Source-stated planning-record quantity

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

CN0143258GY · 2026-06-05

Complete construction of partially constructed dwelling, covered barbecue area building, rear garden landscaping and all associated works and services

1 units · Source-stated event-specific quantity
340 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.