Save this project to account
New Application · decision due 12 Nov 2026Pre-decision · not yet granted

Energy, Letter, Moycullen, Co. Galway

Moycullen, Galway · Galway County Council · Plan 2661584 · PB ref PB-2773066872

for; (1) Amendments to the permitted Ardderroo Synchronous Condenser (Galway County Council Reference No. 23/60641, 24/61485, 25/60575 and 25/61825) comprising repositioning of cooling equipment and provision of 1 no. container within the synchronous condenser compound, a revised footprint of the 110kV electrical compound...

Indicative value Not listed PB indicative band
Units applied for Not listed public application record
Floor area Not listed no reliable figure indexed
Decision due 12 Nov 2026 public planning date
Commenced None indexed public commencement index
Applied for, not granted

The record describes what is sought. Nothing is permitted until the authority decision.

Application scope

Package signals below are limited to wording in the public application record.

Not procurement evidence

No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.

Opportunity & supplier intelligence

What is known, and what may happen next

Source-linked

Timing is a planning-stage outlook, not a tender, award, contractor appointment, supplier appointment or guaranteed procurement date.

Likely procurement timing Decision-dependent

The application is pre-decision. The earliest credible supplier window is after the public decision milestone on 12 Nov 2026; no procurement timetable is published.

Decision due 12 Nov 2026 / Confidence: Medium
Decision deadline 12 Nov 2026

Public planning decision due date; the authority may update it.

Open evidence
Commencement activity No linked activity indexed

No commencement indexed / A scheme cannot commence under this application before permission.

Source limited
Drawings availability Drawing availability not indexed

No drawing entry is available in this lead's bounded document evidence.

Source limited

Confirmed application scope

for; (1) Amendments to the permitted Ardderroo Synchronous Condenser (Galway County Council Reference No. 23/60641, 24/61485, 25/60575 and 25/61825) comprising repositioning of cooling equipment and provision of 1 no. container within the synchronous condenser compound, a revised footprint of the 110kV electrical compound, revision of the 110kV underground cabling route to Knockranny substation and provision of a new access road and widening of the existing road to accommodate the revised underground electrical...

Ref 2661584 Source-linked Official application description for exact planning reference 2661584
Open scope evidence

Public source roles

Buffy Letter Ltd
Applicant / promoter on the public planning record
Application role only; current development or appointment status is not confirmed.

Explicit source signals only

1 package
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

2661584 Explicit description / Source-linked Source
Confidence & provenance 1 official source
Authority
Galway County Council
Exact reference
2661584
Evidence reviewed
26 Sep 2026
Confidence
Source-linked

Facts come from the indexed public planning record and any bounded structured document evidence. No request-time official fetch, tender, award or appointment inference is used.

Application-stage scope

What the public record evidences

2 source-supported signals
Energy

Energy

The public application record identifies energy in the submitted planning scope.

2661584Explicit application record
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

2661584Explicit description signal

Only source-supported scope signals are shown; generic trade padding is omitted.

Project facts

Named source parties

Promoter
Buffy Letter Ltd
Planning agent
Adrian Moran Care of Mko
Agent address
Tuam Rd Galway
Official description

Application text

for; (1) Amendments to the permitted Ardderroo Synchronous Condenser (Galway County Council Reference No. 23/60641, 24/61485, 25/60575 and 25/61825) comprising repositioning of cooling equipment and provision of 1 no. container within the synchronous condenser compound, a revised footprint of the 110kV electrical compound, revision of the 110kV underground cabling route to Knockranny substation and provision of a new access road and widening of the existing road to accommodate the revised underground electrical cabling. (2) Amendment to the Knockranny Wind Farm grid connection (permitted under An Coimisiún Pleanála Reference No. PL07.318723), comprising revised underground electrical (33kV) and communications cabling route to connect to the 110kV electrical compound. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development. Beidh an fhorbairt bheartaithe comhdhéanta de: (1) Leasuithe ar an gComhdhlúthadóir Sioncronach Ardderroo ceadaithe (Uimhreacha Tagartha Chomhairle Chontae na Gaillimhe 23/60641, 24/61485, 25/60575 agus 25/61825) lena n-áirítear athshuíomh trealaimh fhuaraithe agus soláthar de 1 uimh. coimeádáin laistigh de chomhdhúil an chomhdhlúthadóra shioncronach, lorg athbhreithnithe do chomhdhúil leictreach 110kV, athbhreithniú ar an mbealach cáblaithe 110kV faoi thalamh go dtí fostáisiún Knockranny agus soláthar bóthair rochtana nua agus leathnú an bhóthair reatha chun freastal ar an gcábla leictreach faoi thalamh athbhreithnithe. (2) Leasú ar nasc eangach Feirm Gaoithe Knockranny (ceadaithe faoi Uimhir Thagartha An Coimisiún Pleanála PL07.318723), lena n-áirítear bealach athbhreithnithe do chábla leictreach (33kV) agus cumarsáide faoi thalamh chun nascadh leis an gcomhdhúil leictreach 110kV. Ullmhaíodh Ráiteas Tionchair Natura (NIS) i ndáil leis an bhforbairt bheartaithe

Source-aware chronology

Application to site progress

Empty lanes explain their state.
AppealsAn Coimisiún Pleanála
  1. Appeal No appeal possible yet The application has not been decided.
CommencementPublic commencement index
  1. Commenced No commencement indexed A scheme cannot start before it is permitted.
CompletionPublic completion projection
  1. Completed Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Evidence register

Source, scope and limits

Public planning record
Application description and scale 2661584

for; (1) Amendments to the permitted Ardderroo Synchronous Condenser (Galway County Council Reference No. 23/60641, 24/61485, 25/60575 and 25/61825) comprising repositioning of cooling equipment and provision of 1 no. container within the synchronous condenser compound, a revised footprint of the 110kV electrical compound, revision of the 110kV underground cabling route to Knockranny substation and provision of a new access road and widening of the existing road to accommodate the revised underground electrical cabling. (2) Amendment to the Knockranny Wind Farm grid connection (permitted under An Coimisiún Pleanála Reference No. PL07.318723), comprising revised underground electrical (33kV) and communications cabling route to connect to the 110kV electrical compound. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development. Beidh an fhorbairt bheartaithe comhdhéanta de: (1) Leasuithe ar an gComhdhlúthadóir Sioncronach Ardderroo ceadaithe (Uimhreacha Tagartha Chomhairle Chontae na Gaillimhe 23/60641, 24/61485, 25/60575 agus 25/61825) lena n-áirítear athshuíomh trealaimh fhuaraithe agus soláthar de 1 uimh. coimeádáin laistigh de chomhdhúil an chomhdhlúthadóra shioncronach, lorg athbhreithnithe do chomhdhúil leictreach 110kV, athbhreithniú ar an mbealach cáblaithe 110kV faoi thalamh go dtí fostáisiún Knockranny agus soláthar bóthair rochtana nua agus leathnú an bhóthair reatha chun freastal ar an gcábla leictreach faoi thalamh athbhreithnithe. (2) Leasú ar nasc eangach Feirm Gaoithe Knockranny (ceadaithe faoi Uimhir Thagartha An Coimisiún Pleanála PL07.318723), lena n-áirítear bealach athbhreithnithe do chábla leictreach (33kV) agus cumarsáide faoi thalamh chun nascadh leis an gcomhdhúil leictreach 110kV. Ullmhaíodh Ráiteas Tionchair Natura (NIS) i ndáil leis an bhforbairt bheartaithe

AuthorityGalway County Council
Reference2661584
StatusChecked 26 Sep 2026
Open official record