Large residential · Co. Kerry
Ballybunion, co kerry
Granted 21 Dec 2017
We no longer update this application, so we can't email you about it. Get new planning applications in Ballybunion by email
Key facts
- Planning application 07991270 at Ballybunion, Co. Kerry: ~101 homes.
- It was received by Kerry County Council on 19 Sep 2017.
- Status: Granted 21 Dec 2017.
Source: the Kerry County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Ballybunion · Planning applications in Co. Kerry
Council register
The council's register shows: Decision to grant on 21 Dec 2017.
Search the Kerry planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
~101 homes
CONSTRUCT (1) 101 DWELLINGS COMPRISING OF: 54 NO. 2 STOREY 3 BEDROOM SEMI DETACHED DWELLINGS, 3 NO. 2 STOREY 3 BEDROOM DETACHED DWELLINGS, 22 NO. 2 STOREY 3 BEDROOM TERRACE / END OF TERRACE DWELLINGS, 12 NO. 2 STOREY 4 BEDROOM SEMI DETACHED DWELLINGS, 10 NO. 2 STOREY 4 BEDROOM DETACHED DWELLINGS, TOGETHER WITH ANCILLARY SITE WORKS INCLUDING, ESTATE ACCESS ROADWAYS, SITE SERVICES AND OTHER ASSOCIATED SITE WORKS, (2) OUTLNE PLANNING PERMISSION TO CONSTRUCT A 1370 SQ/M2 CHILDCARE FACILITY AND 14 NO. APARTMENTS ALL
- Location
- Ballybunion, Co. Kerry Map
- Council
- Kerry County Council
- Planning reference
- 07991270
Numbers and dates
- Homes
- ~101estimated from the application
- Estimated construction value
- €14m to €28mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 19 Sep 2017
- Granted
- 21 Dec 2017
- Site start notified
- 2 Feb 2018
Timeline
- Application received
- Granted
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 07991270 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Kerry County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 2 Feb 2018Notice filed · phase 1 · To build 3no housesView the site start
- 28 Jun 2018Notice filed · phase 2 · Build 4no houses on Site 10, 11, 12 and 13.View the site start
- 15 Nov 2019Notice filed · phase 3 · To Build 2no housesView the site start
- Completion certificate recordedRecorded in Nov 2019 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.