Mixed use · Co. Kerry
Listowel business park, clieveragh, listowel, Co. Kerry
Granted 9 Jul 2019 (final grant issued 12 Aug 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Listowel by email
Key facts
- Planning application 18906 at Listowel Business Park, Clieveragh, Listowel, Co. Kerry: Light industrial building containing 5 no food manufacturing…
- It was received by Kerry County Council on 19 Sep 2018.
- Status: Granted 9 Jul 2019 (final grant issued 12 Aug 2019).
Source: the Kerry County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Listowel · Planning applications in Co. Kerry
Council register
The council's register shows: Granted on 9 Jul 2019.
Search the Kerry planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Light industrial building containing 5 no food manufacturing…
CONSTRUCT A LIGHT INDUSTRIAL BUILDING CONTAINING 5 NO FOOD MANUFACTURING WAREHOUSE UNITS, 1 NO FOOD DEVELOPMENT/TRAINING KITCHEN, 1 NO OFFICE, CANTEEN, TOILETS, STORAGE AREAS AND ANCILLARY ACCOMMODATION, COMPLETE WITH NEW VEHICULAR ENTRANCE, EXTERNAL CAR PARKING AREAS, GAS COMPOUND, BIN ENCLOSURES, EXTERNAL SMOKING AREA, EXTENSIVE LANDSCAPING EXTERNAL LIGHTING AND ASSOCIATED EXTERNAL WORKS
- Location
- Listowel, Co. Kerry Map
- Council
- Kerry County Council
- Planning reference
- 18906
Numbers and dates
- Project type
- Mixed use
- Received
- 19 Sep 2018
- Decision to grant
- 9 Jul 2019
- Final grant
- 12 Aug 2019
- Site start notified
- 24 May 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 18906 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Kerry County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 24 May 2021Notice filed · A light industrial building containing 5 No. food manufacturing warehouse units, 1 no...View the site start
- Completion certificate recordedRecorded in May 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.