Commercial fit-out · Co. Kerry

Matt talbot road, tralee, co kerry

Granted 8 Jul 2020 (final grant issued 11 Aug 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Tralee by email

Key facts

  • Planning application 20356 at Matt Talbot Road, Tralee, Co Kerry: Retention of existing front elevation of the garage as constructed.
  • It was received by Kerry County Council on 16 Apr 2020.
  • Status: Granted 8 Jul 2020 (final grant issued 11 Aug 2020).
  • Work was due to start on 2 Jan 2021, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Kerry County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Tralee · Planning applications in Co. Kerry

Council register

The council's register shows: Granted on 8 Jul 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Retention of existing front elevation of the garage as constructed

(A) RETAIN THE EXISTING FRONT ELEVATION OF THE GARAGE AS CONSTRUCTED, (B) RETAIN THE REAR EXTENSION AS CONSTRUCTED, (C) RETAIN THE EXISTING SIGNAGE LOCATED AT THE SOUTH CORNER OF THE PROPERTY, (D) RETAIN ALL OF THE ABOVE WITHIN REVISED SITE BOUNDARIES, (E) CONSTRUCT A SINGLE STOREY EXTENSION COMPRISING A REPOSING ROOM AND LOBBY WITH MINOR INTERNAL RENOVATIONS WITHIN THE EXISTING BUILDING, (F) CONSTRUCT AN EXTERNAL CANOPY, (G) REPLACE THE EXISTING EXTERNAL BRICK FINISH AND TIMBER FACADES WITH A SMOOTH PLASTER FINISH, (H) NEW SINGAGE TO EXISTING AND PROPOSED ELEVATIONS AND (I) ALL ANCILLARY SITE WORKS

Location
Tralee, Co. Kerry Map
Planning reference
20356

Numbers and dates

Project type
Commercial fit-out
Received
16 Apr 2020
Decision to grant
8 Jul 2020
Final grant
11 Aug 2020
Site start notified
2 Jan 2021

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 2 Jan 2021, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 20356 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Kerry County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 2 Jan 2021Notice filed · Material alterations within the existing building comprising swapping the existing...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Tralee

Get alerts for TraleeFree. We email you when new applications appear.

Free email alerts

Get new Tralee projects by email

New applications, decisions and site starts in Tralee, Co. Kerry. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options