Key facts
- Planning application 21489 at Ballybunion (sandhill Road), Co. Kerry: 6 homes.
- It was received by Kerry County Council on 7 May 2021.
- Status: Granted on appeal 2 Aug 2022 (Granted 17 Sep 2021 by the council).
- Work started on site on 15 Apr 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Kerry County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 17 Sep 2021.
Search the Kerry planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
6 homes
CONSTRUCT 6 NO. SEMI DETACHED HOUSES ON SITES 12, 13, 14, 15, 16 AND 17 AND ALL ASSOCIATED SITE WORKS
- Location
- Ballybunion (sandhill Road), Co. Kerry Map
- Council
- Kerry County Council
- Planning reference
- 21489
Numbers and dates
- Homes
- 6
- Project type
- Small multi-unit
- Received
- 7 May 2021
- Council decision
- 17 Sep 2021
- Appeal lodged
- 14 Oct 2021
- Granted on appeal
- 2 Aug 2022
- Site start
- 15 Apr 2024
Timeline
- Application received
- Granted by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 21489 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealGrant permission with revised conditions · 311662 / 2 Aug 2022View the appeal record
How we know this
From the Kerry County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 15 Apr 2024Work started · phase 1 · To construct 2no semi detached houses on sites 16 and 17, Fairway Drive, The Links.View the site start
- 6 May 2024Work started · phase 2 · To construct 4 no 2 storey semi detached houses of traditional blockwork constructional...View the site start
- 26 Oct 2026Work started · phase 3 · To construct 4 no. semi-detached houses on sites 12, 13, 14 and 15.View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.