Commercial new build · Co. Kerry

IDA Industrial Estate, Tiernaboul, Killarney Co. Kerry

Granted 19 Mar 2025

Key facts

  • Planning application 2460783 at IDA Industrial Estate, Tiernaboul, Killarney Co. Kerry: Revised industrial development previously granted permission under…
  • It was received by Kerry County Council on 11 Oct 2024.
  • Status: Granted 19 Mar 2025.
  • Work started on site on 30 Jun 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Kerry County Council planning register, checked 2 Jun 2026. Open the council's file

More planning applications in Tiernaboul · Planning applications in Co. Kerry

What and where

Revised industrial development previously granted permission under…

Planning Permission for a revised industrial development previously granted permission under Planning Register No 16/226 and extended under Planning Register No 16/9226 to construct an 80 metre x 30 metre industrial unit for the purposes of steel manufacturing with associated welfare facilities, external carparking and associated site works at the IDA Industrial Estate, Tiernaboul, Killarney, Co. Kerry.

Location
Tiernaboul, Co. Kerry Map
Planning reference
2460783
Council planning fileGet alertsDownload PDF

Numbers and dates

Project type
Commercial new build
Received
11 Oct 2024
Granted
19 Mar 2025
Site start
30 Jun 2025

Timeline

  1. Application received
  2. Granted
  3. Site start

Site history

This site's history

  1. Earlier permission 169226 for this site: granted 7 Oct 2021.

    CONSTRUCT AN 80 METRE X 30 METRE INDUSTRIAL UNIT FOR PURPOSES OF STEEL MANUFACTURING WITH ASSOCIATED WELFARE FACILITIES, EXTERNAL CAR… Named in this application's description

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work started on site on 30 Jun 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2460783 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Kerry County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Site starts

Commencement notices for this permission

  1. 30 Jun 2025Work started · A New Production Facility Building for Killarney Precision Engineering At The IDA...

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Tiernaboul

Get alerts for TiernaboulFree. We email you when new applications appear.

Free email alerts

Get new Tiernaboul projects by email

New applications, decisions and site starts in Tiernaboul, Co. Kerry. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options