GrantedDecision recorded

Demolition, ESB Networks Killarney Business & Technology Park, Tiernaboul, Co...

Tiernaboul, Kerry · Kerry County Council · Plan 2660098 · PB ref PB-10000291204

The Electricity Supply Board (ESB) are seeking Planning Permission for development consisting of: (a) Refurbishment and internal reconfiguration of the existing depot building; works involving material alterations to the front elevation, including removal and infill of selected openings and provision of a revised window...

Indicative value €500k–1m PB indicative band
Units applied for Not listed public application record
Floor area 644 m² published reliable figure
Decision 1 Apr 2026 public planning date
Commenced None indexed public commencement index
Decision-stage scope

The public decision state is shown, but conditions and later amendments can still change delivery scope.

Application scope

Package signals below are limited to wording in the public application record.

Not procurement evidence

No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.

Opportunity & supplier intelligence

What is known, and what may happen next

Source-linked

Timing is a planning-stage outlook, not a tender, award, contractor appointment, supplier appointment or guaranteed procurement date.

Likely procurement timing Post-decision monitoring

A planning decision is recorded and no linked commencement is indexed. Conditions, procurement and start timing remain unconfirmed.

Decision date 1 Apr 2026. / Confidence: Low
Decision CONDITIONAL

Decision date 1 Apr 2026.

Commencement activity No linked activity indexed

No commencement indexed / This is an index state, not proof that no works have started.

Source limited
Drawings availability Drawing availability not indexed

No drawing entry is available in this lead's bounded document evidence.

Source limited

Confirmed application scope

The Electricity Supply Board (ESB) are seeking Planning Permission for development consisting of: (a) Refurbishment and internal reconfiguration of the existing depot building; works involving material alterations to the front elevation, including removal and infill of selected openings and provision of a revised window arrangement to reflect the internal layout; and, (b) Installation of 3 No. external access ramps with associated handrails/guarding to serve the three entrances; and, (c) installation of a PV...

Ref 2660098 Source-linked Official application description for exact planning reference 2660098

Public source roles

No named firm role is published in this panel's source contract. PlanningBrief does not infer a contractor or supplier.

Explicit source signals only

0 packages

No work package meets the explicit source, reference and locator threshold. PlanningBrief does not pad this list with generic trades.

Confidence & provenance 0 official sources
Authority
Kerry County Council
Exact reference
2660098
Evidence reviewed
2 Jun 2026
Confidence
Source-linked

Facts come from the indexed public planning record and any bounded structured document evidence. No request-time official fetch, tender, award or appointment inference is used.

Application-stage scope

What the public record evidences

1 source-supported signals
Demolition

Demolition

The public application record identifies demolition in the submitted planning scope.

2660098Explicit application record

Only source-supported scope signals are shown; generic trade padding is omitted.

Project facts

Named source parties

Promoter
Electricity Supply Board
Official description

Application text

The Electricity Supply Board (ESB) are seeking Planning Permission for development consisting of: (a) Refurbishment and internal reconfiguration of the existing depot building; works involving material alterations to the front elevation, including removal and infill of selected openings and provision of a revised window arrangement to reflect the internal layout; and, (b) Installation of 3 No. external access ramps with associated handrails/guarding to serve the three entrances; and, (c) installation of a PV solar system, including the installation of PV solar panels on the roof of the existing Depot structure; and, (d) Demolition of the existing single storey link corridor (13.5 m²) between the subject depot building and an adjoining depot building in separate ownership, with making good to exposed wall surfaces; and, (e) Demolition of two single storey outbuildings (165 m² & 175 m² respectively); and, (f) The replacement of the existing sheet roof for the stores building (290 m²), replaced with proposed insulated roof panel system; and, (g) Material alterations to the external elevations of the existing stores building, including the infill and installation of new windows and roller shutter access. The application includes all ancillary works associated with the development located at the existing depot site.

Source-aware chronology

Application to site progress

Empty lanes explain their state.
AppealsAn Coimisiún Pleanála
  1. Appeal No appeal indexed No public appeal record is indexed against this application.
CommencementPublic commencement index
  1. Commenced No commencement indexed No reliable public commencement record is indexed against this permission.
CompletionPublic completion projection
  1. Completed Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Evidence register

Source, scope and limits

Public planning record
Application description and scale 2660098

The Electricity Supply Board (ESB) are seeking Planning Permission for development consisting of: (a) Refurbishment and internal reconfiguration of the existing depot building; works involving material alterations to the front elevation, including removal and infill of selected openings and provision of a revised window arrangement to reflect the internal layout; and, (b) Installation of 3 No. external access ramps with associated handrails/guarding to serve the three entrances; and, (c) installation of a PV solar system, including the installation of PV solar panels on the roof of the existing Depot structure; and, (d) Demolition of the existing single storey link corridor (13.5 m²) between the subject depot building and an adjoining depot building in separate ownership, with making good to exposed wall surfaces; and, (e) Demolition of two single storey outbuildings (165 m² & 175 m² respectively); and, (f) The replacement of the existing sheet roof for the stores building (290 m²), replaced with proposed insulated roof panel system; and, (g) Material alterations to the external elevations of the existing stores building, including the infill and installation of new windows and roller shutter access. The application includes all ancillary works associated with the development located at the existing depot site.

AuthorityKerry County Council
Reference2660098
StatusChecked 2 Jun 2026
Open official record