House extension · Co. Kildare

2 The Oaks, Castletown, Celbridge, Co. Kildare

Granted 23 Nov 2018 (final grant issued 17 Jan 2019)

We no longer update this application, so we can't email you about it. Get new planning applications in Celbridge by email

Key facts

  • Planning application 181060 at 2 The Oaks, Castletown, Celbridge, Co. Kildare: New extension to ground floor with a floor area of 14.7 m².
  • It was received by Kildare County Council on 30 Aug 2018.
  • Status: Granted 23 Nov 2018 (final grant issued 17 Jan 2019).
  • Work was due to start on 18 Apr 2019, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Kildare County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Celbridge · Planning applications in Co. Kildare

Council register

The council's register shows: Granted on 23 Nov 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New extension to ground floor with a floor area of 14.7 m²

(a) New extension to ground floor with a floor area of 14.7 m² including demolition of existing storage, garage all on North/West side of existing dwelling. (b) New extension to front with a floor area of 1.5 m². (c) First floor bedroom extension to rear of existing dwelling with a floor area of 32.2 m² along with No. 2 roof lights to the roof facing North/West. (d) New No. 2 windows to first floor elevation facing South/East with obscure glazing up to 1.8m above floor level. (e) New window to first floor North/West side elevation. (f) New brick façade to front and rear and general alterations along with Retention Permission sought for store to rear garden with a floor area of 25.7 m² not exceeding 3m in height. All

Location
Celbridge, Co. Kildare Map
Planning reference
181060

Numbers and dates

Floor area
74 m²
Project type
House extension
Received
30 Aug 2018
Decision to grant
23 Nov 2018
Final grant
17 Jan 2019
Site start notified
18 Apr 2019

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 18 Apr 2019, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 181060 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Kildare County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 18 Apr 2019Notice filed · New extension to ground floor with a floor area of 14.7sqm including demolition of...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Celbridge

Get alerts for CelbridgeFree. We email you when new applications appear.

Free email alerts

Get new Celbridge projects by email

New applications, decisions and site starts in Celbridge, Co. Kildare. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options