10 year permission
a 10 year permission (to construct development) for a solar farm comprising: the installation of photovoltaic panels on ground mounted frames in rows on a site of C.47.44 hectares, a single storey onsite 38kV substation with compound, with 2 no single storey storage containers, 25 no. invertor stations, ducting & underground electrical cabling, perimeter fencing, 23.no mounted CCTV Cameras, provision of a new access from the L5066/Killadoon Road, provision of internal access tracks, and all associated site development and landscaping works
- Location
- Celbridge, Co. Kildare Map
- Council
- Kildare County Council
- Planning reference
- 18250
- Agent
- Joseph McMenamin & Son (Stranorlar) Ltd
- Builder
- Joseph McMenamin & Son (Stranorlar) Ltd
Key facts
- Project type
- Infrastructure
- Site start
- 22 Nov 2024
Documents and evidence
Check the record
- Council planning fileThe application file 18250 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Kildare County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 22 Nov 2024Work started · Our section of the over all development entails the construction of single storey 38Kv...
- Completion certificate recordedRecorded in Nov 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Sep 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.