Large residential · Co. Kildare

Clonmullen and Gallowshill, Geraldine Road, Athy, Co. Kildare

Granted 7 Jan 2020

We no longer update this application, so we can't email you about it. Get new planning applications in Athy by email

Key facts

  • Planning application 19234 at Clonmullen and Gallowshill, Geraldine Road, Athy, Co. Kildare: 86 homes.
  • It was received by Kildare County Council on 8 Mar 2019.
  • Status: Granted 7 Jan 2020.

Source: the Kildare County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Athy · Planning applications in Co. Kildare

Council register

The council's register shows: Granted on 7 Jan 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

86 homes

phase 2 of a three phase housing development to include (a) erection of 86 residential units comprising 2 no. two storey 140.94 m² 4 bedroom detached dwelling houses (HouseType A), 8 no. two storey 113 m², 3 bedroom semi-detached dwelling houses (Houses Type D), 8 no. two storey, Type E – 114.25 m², Type E1 – 118 m² 3 bedroom semi- detached dwelling houses (House Type E/E1), 24 no. two storey 100 m² 3 bedroom semi-detached dwelling houses (House Type F), 16 no. two storey 89.5 m² 2 bedroom town houses (House Type G), 7 no. two storey apartment blocks (Block I) comprising 14 no. ground floor 73.93 m² 2 bedroom apartments and 14 no. first floor 49.76 m² 1 bedroom apartments to include car parking, bin stores, bicycle stores and boundary wall, (b) new site entrance off Geraldine Road with access road, cycleway and footpath, (c) provide vehicular and pedestrian access to adjoining site to the south west comprising 0.8453 hectares currently zoned “C” New Residential (d) all site development works associated with main access road and phase 2 of the three phase residential development including footpaths, roads, public lighting, attenuation ponds, surface water drains, foul sewer drains, water mains and all other utility services necessary to service the proposed development. This planning application is accompanied by a Natura Impact Statement. There is currently a valid planning application for phase 1 of this three phase housing development, planning register reference 18/921 refers.

Location
Athy, Co. Kildare Map
Planning reference
19234

Numbers and dates

Homes
86
Floor area
7,590 m²
Estimated construction value
€11m to €21mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
8 Mar 2019
Granted
7 Jan 2020
Site start
25 Mar 2025

Timeline

  1. Application received
  2. Granted
  3. Appeal lodged
  4. Appeal decidedAppeal withdrawn S.140(1)(a)
  5. Site start

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Kildare County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 25 Mar 2025Work started · phase 1 · Duplex type i, Nos. 39-42 of: phase 2 of a three phase housing development to include...View the site start
  2. 25 Mar 2025Work started · phase 2 · Duplex type i, Nos. 25-28 of: phase 2 of a three phase housing development to include...View the site start
  3. 25 Mar 2025Work started · phase 3 · Duplex type i, Nos. 47-50 of: phase 2 of a three phase housing development to include...View the site start
  4. 25 Mar 2025Work started · phase 4 · Duplex type i, Nos. 29-32 of: phase 2 of a three phase housing development to include...View the site start
  5. 25 Mar 2025Work started · phase 5 · Duplex type i, Nos. 57-60 of: phase 2 of a three phase housing development to include...View the site start
  6. 25 Mar 2025Work started · phase 6 · Duplex type i, Nos. 53-56 of: phase 2 of a three phase housing development to include...View the site start
  7. 26 Mar 2025Work started · phase 7 · 58 dwellngs of: phase 2 of a three phase housing development to include (a) erection of...View the site start
  8. 27 Mar 2025Work started · phase 8 · Duplex type i, Nos. 43-46 of: phase 2 of a three phase housing development to include...View the site start
  9. Partial completion certificate recordedRecorded in Mar 2025 · 16 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
  10. Partial completion certificate recordedRecorded in Mar 2025 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
  11. Partial completion certificate recordedRecorded in Mar 2025 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Athy

Get alerts for AthyFree. We email you when new applications appear.

Free email alerts

Get new Athy projects by email

New applications, decisions and site starts in Athy, Co. Kildare. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options