Commercial new build · Co. Kildare
IDA Industrial Estate, Monread Road, Naas, Co. Kildare
Granted 10 Jan 2022 (final grant issued 21 Feb 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Naas by email
Key facts
- Planning application 211410 at IDA Industrial Estate, Monread Road, Naas, Co. Kildare: 724 m² temperature controlled extension to the existing manufacturing…
- It was received by Kildare County Council on 1 Oct 2021.
- Status: Granted 10 Jan 2022 (final grant issued 21 Feb 2022).
Source: the Kildare County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Naas · Planning applications in Co. Kildare
Council register
The council's register shows: Granted on 10 Jan 2022.
Search the Kildare planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
724 m² temperature controlled extension to the existing manufacturing…
to erect a 724 m² temperature controlled extension to the existing manufacturing facility with ridge height not exceeding 12.65m high to the South west facing elevation, complete with internal minor modifications and associate site ancillary works
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Naas, Co. Kildare Map
- Council
- Kildare County Council
- Planning reference
- 211410
Numbers and dates
- Floor area
- 724 m²
- Project type
- Commercial new build
- Received
- 1 Oct 2021
- Decision to grant
- 10 Jan 2022
- Final grant
- 21 Feb 2022
- Site start notified
- 17 Aug 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 211410 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Kildare County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 17 Aug 2022Notice filed · Construction of a temperature controlled extension to the existing manufacturing...View the site start
- Completion certificate recordedRecorded in Aug 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.