Mixed use · Co. Kildare

Kildare Innovation Campus (KIC), Barnhall Meadows, Leixlip

Granted 7 Sep 2023 (final grant issued 22 Jan 2024)

We no longer update this application, so we can't email you about it. Get new planning applications in Leixlip by email

Key facts

  • Planning application 2360047 at Kildare Innovation Campus (KIC), Barnhall Meadows, Leixlip: Will consist of Demolition of existing Buildings No’s 7.
  • It was received by Kildare County Council on 18 Jul 2023.
  • Status: Granted 7 Sep 2023 (final grant issued 22 Jan 2024).

Source: the Kildare County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Leixlip · Planning applications in Co. Kildare

Council register

The council's register shows: Granted on 7 Sep 2023.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Will consist of Demolition of existing Buildings No’s 7

will consist of Demolition of existing Buildings No’s 7, 8 and 9 (total gfa c. 84,838 m²). - Existing Buildings No’s 1 – 6 will be retained for deep tech and innovation related uses (total gfa c.42,862 m²) - Construction of 2 no. new deep tech buildings and 4 no. new data centre buildings, all including ancillary office spaces. The deep tech buildings will have an overall maximum height of c.16m and vary in size from30,945 m² – 41,190 m² with a combined total gfa of c. 72,135 m². The data centres will be c.15 m in height to parapet and c.16.5m in height to top of roof plant screening. The data centres will vary in size from 13,225 m² – 21,000 m² with a combined total gfa of c. 76,225 m². All buildings will be provided with Solar PV panels at roof level and green walls along selected elevations. - The new deep tech buildings (A1 & A2) will be provided with service yard areas, loading docks, car parking, access roads, security fencing/gates and landscaping. The deep tech buildings will include rainwater harvesting tanks and green roofs over office areas. - Each data centre (B1, C1, C2 & C3) will include data halls, admin blocks (comprising offices, breakroom, loading dock, storage, and ancillary areas) and a variety of mechanical and electrical plant areas/structures including battery storage rooms and mechanical rooms. Car parking, access roads, security fencing/gates, gate houses and landscaping will also be provided. - B1 will include 14 no. fuel oil generators, MV rooms and associated mechanical flues. C1 – C3 will each include 22 no. fuel oil generators, MV rooms and associated mechanical flues (each c.18.6m high). Car parking, access roads, security fencing/gates, gate houses and landscaping will also be provided. - 2 no. district heating pump house areas and inground piping for district heating system. - Construction of a Replacement 110kV Gas Insulated Switchgear (GIS) Substation adjacent to the existing 110kV Rinawade Substation. The current Air Insulated Switchgear (AIS) substation known as the Rinawade 110kV sub is fed by 2 x 110kV Overhead lines. The new substation will connect to these overhead lines via short runs of underground cable. The replacement 110kV substation will include 6 No. transformers, with client control building and a 2 storey GIS substation building within a 2.4m high fenced compound. - Decommissioning and removal of the existing 110kV Rinawade substation. - Construction of an on-site energy centre to provide to the nation

Location
Leixlip, Co. Kildare Map
Planning reference
2360047

Numbers and dates

Project type
Mixed use
Received
18 Jul 2023
Decision to grant
7 Sep 2023
Final grant
22 Jan 2024
Site start notified
12 Dec 2024

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Kildare County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 12 Dec 2024Notice filed · phase 1 · Construction of a new 110kV Gas Insulated Switchgear (GIS) Substation Building to...View the site start
  2. 18 Dec 2024Notice filed · phase 2 · Construction of a new Client Control Building to service a new data centre within...View the site start
  3. 9 May 2025Notice filed · phase 3 · Construction of i) a single storey building for use as electrical rooms for electronic...View the site start
  4. Partial completion certificate recordedRecorded in May 2025 · 4 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Leixlip

Get alerts for LeixlipFree. We email you when new applications appear.

Free email alerts

Get new Leixlip projects by email

New applications, decisions and site starts in Leixlip, Co. Kildare. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options