Public / civic · Co. Kilkenny
St Michael's National School, Dundaryark Danesfort, Co. Kilkenny
Granted 13 Oct 2023 (final grant issued 15 Nov 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Kilkenny by email
Key facts
- Planning application 2360378 at St Michael's National School, Dundaryark Danesfort, Co. Kilkenny: New single storey classroom extension to the rear of the school…
- It was received by Kilkenny County Council on 22 Aug 2023.
- Status: Granted 13 Oct 2023 (final grant issued 15 Nov 2023).
Source: the Kilkenny County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 13 Oct 2023.
Search the Kilkenny planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New single storey classroom extension to the rear of the school…
The development will consist of the construction of a new single storey classroom extension to the rear of the school building, provision of a temporary construction access roadway, and upgrade of the existing on-site wastewater treatment system including polishing filter together with all associated site & ancillary works
- Location
- Dundaryark Danesfort, Co. Kilkenny Map
- Council
- Kilkenny County Council
- Planning reference
- 2360378
Numbers and dates
- Project type
- Public / civic
- Received
- 22 Aug 2023
- Decision to grant
- 13 Oct 2023
- Final grant
- 15 Nov 2023
- Site start notified
- 24 Jun 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 2360378 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Kilkenny County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 24 Jun 2024Notice filed · Construction of a new single storey classroom extension including link corridor to the...View the site start
- Completion certificate recordedRecorded in Jun 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area