Summerhill Lane, Portlaoise, Co. Laois
Granted 1 May 2018 (final grant issued 14 Jun 2018)
We no longer update this application, so we can't email you about it. Get new planning applications in Portlaoise by email
Key facts
- Planning application 17396 at Summerhill Lane, Portlaoise, Co. Laois: 87 homes.
- It was received by Laois County Council on 24 Jul 2017.
- Status: Granted 1 May 2018 (final grant issued 14 Jun 2018).
Source: the Laois County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Portlaoise · Planning applications in Co. Laois
Council register
The council's register shows: Granted on 1 May 2018.
Search the Laois planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
87 homes
provide 87 no. two-storey dwellings (38 no. 4-bedroom semi-detched houses, 6 no. 3-bedroom semi-detched houses, 3 no. 5-bedroom detched houses, 22 no. 4-bedroom end of terrace houses and 18 no. 3-bedroom terraced houses) and a single storey creche; lighting; landscaping; bundary treatments; and all associated site development works
- Location
- Portlaoise, Co. Laois Map
- Council
- Laois County Council
- Planning reference
- 17396
Numbers and dates
- Homes
- 87
- Floor area
- 12,076 m²
- Estimated construction value
- €18m to €24mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 24 Jul 2017
- Decision to grant
- 1 May 2018
- Final grant
- 14 Jun 2018
- Site start notified
- 7 Sep 2018
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 17396 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Laois County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 7 Sep 2018Notice filed · phase 1 · Construction of eight semi-detached and terraced houses (Numbers 1 to 8)View the site start
- 21 Nov 2018Notice filed · phase 2 · Construction of twelve semi-detached and terraced houses (Plot Numbers 9 to 20)...View the site start
- 29 Oct 2021Notice filed · phase 3 · Construction of Houses 69-90 Ashewood Walk, Portlaoise.View the site start
- 15 Jun 2022Notice filed · phase 4 · Construction of Units 81-82, 91-98 and 156-161 Ashewood WalkView the site start
- 14 Jul 2023Notice filed · phase 5 · Construction of Units 99-104 Ashewood WalkView the site start
- Completion certificate recordedRecorded in Sep 2018 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2018 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2018 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.