Site start · Co. Laois

An Sráidbhaile, Laois

Granted 27 Nov 2018 (final grant issued 14 Jan 2019)

Key facts

  • Site start record 18/301 at An Sráidbhaile, Co. Laois: 17 homes.
  • The planning authority is Laois County Council.
  • Status: Granted 27 Nov 2018 (final grant issued 14 Jan 2019).

Source: the Laois County Council planning register, as last seen on 22 Jun 2026. Search the council's register

Planning applications in Co. Laois

Council register

The council's register shows: Granted on 27 Nov 2018.

Application details as we last saw them in the national register on 22 Jun 2026.

What and where

17 homes

Commencement Notice to construct 17 no. residential dwellings, comprising 2 no 2 storey two-bedroom mid-terrace houses, 1 no 2 storey three- bedroom mid- terrace houses, 6 no. 2 storey three- bedroom end- terrace houses, 6 no 2 storey four- bedroom semi- detached houses, and 2 no 2 storey detached four- bedroom houses; public open space areas, car parking spaces, new vehicular access and egress

Description as published by the council. Its text starts part-way through a sentence.

Location
An Sráidbhaile, Co. Laois Map
Planning reference
18/301
Application type
Commencement Notice
Owner named on the notice
Mark Coleman Construction Ltd
Agent named on the notice
Mark Coleman Construction Ltd

Numbers and dates

Homes
17
Floor area
1,968 m²
Estimated construction value
€2.9m to €3.8mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Small multi-unit
Received
17 May 2018
Decision to grant
27 Nov 2018
Final grant
14 Jan 2019
Site start notified
26 Aug 2021

Documents and evidence

Check the record

How we know this

From the Laois County Council planning register, as last seen on 22 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 26 Aug 2021Notice filed · phase 1 · to construct 31 no. residential dwellings, comprising 2 no 2 storey two-bedroom terrace...View the site start
  2. 21 Dec 2023Notice filed · phase 2 · to construct 24 no. residential dwellings, comprising 4 no 2 storey two-bedroom terrace...View the site start
  3. 8 Jul 2024Notice filed · phase 3 · to construct 17 no. residential dwellings, comprising 2 no 2 storey two-bedroom...View the site start
  4. Completion certificate recordedRecorded in Aug 2021 · 20 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  5. Completion certificate recordedRecorded in Aug 2021 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  6. Partial completion certificate recordedRecorded in Jul 2024 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near An Sráidbhaile

Get alerts for Co. LaoisFree. We email you when new applications appear.

Free email alerts

Get new Laois projects by email

New applications, decisions and site starts in Co. Laois. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options