Small multi-unit · Co. Limerick
Rathkeale Road, Adare, Co. Limerick.
Granted 21 Aug 2020
Since you last looked
Worked out in this browser from the record's own dates. We do not send emails about it.
Council register
The council's register shows: Granted on 21 Aug 2020.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
17 homes
the construction of a housing development of 17 no. residential units comprising of the following: (a) 8 no. two storey 4-bed semi-detached dwellings, and (b) 1 no. residential block (part 2 storey, part 3 storey) consisting of (i) 6 no. 2-bed terraced townhouses over ground & first floor, (ii) 2 no. 3-bed terraced townhouses over ground & first floor, and (iii) 1 no. 3-bed apartment on second floor, together with new pedestrian and vehicular entrance access via existing public car park, boundary treatments, landscaping, and all ancillary site works
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Adare, Co. Limerick Map
- Planning reference
- 19684
Key facts
- Homes
- 17
- Floor area
- 2,210 m²
- Estimated construction value
- €3.3m to €6.0mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Small multi-unit
- Received
- 10 Jul 2019
- Granted
- 21 Aug 2020
- Site start
- 13 Sep 2023
Timeline
- Application received
- Granted
- Site start
Documents and evidence
Check the record
- Council planning fileThe application file 19684 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Limerick City and County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 13 Sep 2023Work started · phase 1 · Construction of 8 no. 4-bed semi- detached dwellings
- 21 Sep 2023Work started · phase 2 · Construction of 6 no. 2-bed terraced townhouses, 2 no. 3-bed terraced and 1 no. 3-bed...
- Completion certificate recordedRecorded in Sep 2023 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 3 Oct 2026.
- Completion certificate recordedRecorded in Sep 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 3 Oct 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.