Public / civic · Co. Louth
St Oliver's National School, Ballymakenny Road, Drogheda, Co. Louth
Granted on appeal 12 Nov 2019 (Decision to grant 25 Jul 2019 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Drogheda by email
Key facts
- Planning application 19451 at St Oliver's National School, Ballymakenny Road, Drogheda, Co. Louth: 1 no. single storey prefab unit.
- It was received by Louth County Council on 11 Jun 2019.
- Status: Granted on appeal 12 Nov 2019 (Decision to grant 25 Jul 2019 by the council).
Source: the Louth County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Drogheda · Planning applications in Co. Louth
Council register
The council's register shows: Decision to grant on 25 Jul 2019.
Search the Louth planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
1 no. single storey prefab unit
Permission for 1 no. single storey prefab unit consisting of 2 no. classrooms and store/office for pre-school/after school use, along with all associated site works.
- Location
- Drogheda, Co. Louth Map
- Council
- Louth County Council
- Planning reference
- 19451
Numbers and dates
- Homes
- ~1estimated from the application
- Project type
- Public / civic
- Received
- 11 Jun 2019
- Council decision
- 25 Jul 2019
- Appeal lodged
- 13 Aug 2019
- Granted on appeal
- 12 Nov 2019
- Site start notified
- 18 Feb 2020
Timeline
- Application received
- Decision to grant by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 19451 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealGrant permission with revised conditions · 305153 / 12 Nov 2019View the appeal record
How we know this
From the Louth County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 18 Feb 2020Notice filed · single storey prefab unit consisting of 2 no. classrooms and store/office for...View the site start
- Completion certificate recordedRecorded in Feb 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.