Planning record · Co. Louth
Ceol Na Mara Mooretown Lane, Dublin Road Lurgangreen, Dundalk Co Louth
Granted 16 Dec 2022 (final grant issued 25 Jan 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Louth by email
Key facts
- Planning application 22417 at Ceol na Mara Mooretown Lane, Dublin Road Lurgangreen, Dundalk Co Louth: New shed and associated site works.
- It was received by Louth County Council on 26 May 2022.
- Status: Granted 16 Dec 2022 (final grant issued 25 Jan 2023).
- Work was due to start on 26 Jun 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Louth County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 16 Dec 2022.
Search the Louth planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New shed and associated site works
Permission for a new shed and associated site works
- Location
- Dublin Road Lurgangreen, Co. Louth Map
- Council
- Louth County Council
- Planning reference
- 22417
Numbers and dates
- Homes
- 1
- Floor area
- 82 m²
- Project type
- Planning record
- Received
- 26 May 2022
- Decision to grant
- 16 Dec 2022
- Final grant
- 25 Jan 2023
- Site start notified
- 26 Jun 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 22417 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Louth County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 26 Jun 2023Notice filed · Construction of new shed and assocaited site worksView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.