Commercial new build, Dunleer, Louth - Planning Application 22879

Louth / Dunleer / Dunleer, Louth

Est. value €10m–30m
Units Not listed
Floor area 7,536 m²
Commenced 26 Aug 2024

Source-linked planning record

Commercial new build, Dunleer, Louth - Planning Application 22879

Louth / Dunleer / Dunleer, Louth
PB ref
PB-318650
Plan ref
22879
Authority
Louth County Council
Stage / date
Commencement / 26 Aug 2024
Est. value band
€10m–30m
Units / floor
7,536 m²
Project class
Commercial new build
Promoter
not available yet
Architect / agent
Meegan Builders (Castleblayney) Ltd

Source: http://www.eplanning.ie/LouthCC/AppFileRefDetails/22879/0

Key facts

Lead summary

Source
Owner-supplied commencement export
Planning authority
Louth County Council
Application reference
22879
Applicant
not available yet
Agent
Meegan Builders (Castleblayney) Ltd
Decision stage
Commencement
Commenced
26 Aug 2024
Floor area
7,536 m²
Builder / developer
Meegan Builders (Castleblayney) Ltd

Official description

Verbatim source text

Permission for 1. a total floor area of7536.3 m² part single storey, part 2 storey warehouse facility including, 2. a total of 7111.5 m² ground floor warehouse; 3. a total of 424.8 m² of office and associated staff facilities over 2 floors, 4. an external canopy over part of an existing industrial yard; 5. an extension to the existing industrial yard; 6. PV panels on roof; 7. and all associated site works

Verify against official source

Project team

Named source parties

Promoter
not available yet
Planning agent
Meegan Builders (Castleblayney) Ltd
Builder / developer
Meegan Builders (Castleblayney) Ltd

Lifecycle timeline

Application to site progress

  1. Applied

    11 Nov 2022 22879
  2. Decision

    Conditional 24 Jul 2023
  3. Appeal

    No appeal indexed No public appeal record is indexed against this application.
  4. Commenced

    26 Aug 2024 Work started · Construction of a new warehouse and ancillary offices with all associated site works
  5. Completed

    Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.

Likely trades & supplier leads

Inferred from scheme type and scale

ComplianceElectricalFire SafetyFit-outHealth & SafetyMain contractorMechanicalSecuritySignageSolar/Energy
Board this lead Create alert