Planning application · Co. Louth

Carroll Village Shopping Centre, The Long Walk, Dundalk Co Louth

Granted on appeal 21 Aug 2024 (Granted 12 Jun 2023 by the council)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Louth by email

Key facts

  • Planning application 22921 at Carroll Village Shopping Centre, The Long Walk, Dundalk Co Louth: Partial demolition of the existing shopping centre building…
  • It was received by Louth County Council on 28 Nov 2022.
  • Status: Granted on appeal 21 Aug 2024 (Granted 12 Jun 2023 by the council).
  • Work started on site on 30 Jul 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Louth County Council planning register, as last seen on 2 Jun 2026. Open the council's file

Planning applications in Co. Louth

Council register

The council's register shows: Granted on 12 Jun 2023.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Partial demolition of the existing shopping centre building…

Permission for partial demolition of the existing shopping centre building and the construction of a new four storey Primary Care Centre including (a) General Practitioners Surgery, (b) Pharmacy Unit and (c) HSE accommodation, external plant area, relocation of existing site access, car parking and set down area, erection of access control barriers, new totem sign, general wall mounted signage, new elevational treatment to north facade of the Carroll Village Shopping Centre, site lighting, hard and soft landscaping and all associated site works **Significant further information received on 22.5.23**

Location
The Long Walk, Co. Louth Map
Planning reference
22921

Numbers and dates

Received
28 Nov 2022
Council decision
12 Jun 2023
Appeal lodged
7 Jul 2023
Granted on appeal
21 Aug 2024
Site start
30 Jul 2026

Timeline

  1. Application received
  2. Granted by the council
  3. Appeal lodged
  4. Appeal decidedGrant permission with revised conditions
  5. Site start

Outlook

What happens next

Work started on site on 30 Jul 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the Louth County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 30 Jul 2026Work started · Partial demolition of the existing Carroll Village Shopping Centre building and the...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near The Long Walk

Get alerts for Co. LouthFree. We email you when new applications appear.

Free email alerts

Get new Louth projects by email

New applications, decisions and site starts in Co. Louth. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options