Back to leads
Est. value
€250k–500k
Units
1
Floor area
58 m²
Commenced
18 Oct 2024
Commencement
1 dwelling, Dundalk, Louth - Planning Application 22984
Louth / Dundalk / Dundalk, Louth
Source-linked planning record
1 dwelling, Dundalk, Louth - Planning Application 22984
Louth / Dundalk / Dundalk, Louth- PB ref
- PB-319830
- Plan ref
- 22984
- Authority
- Louth County Council
- Stage / date
- Commencement / 18 Oct 2024
- Est. value band
- €250k–500k
- Units / floor
- 1 / 58 m²
- Project class
- Protected structure
- Promoter
- P.j. & E.j. Doherty Ltd
- Architect / agent
- P.j. & E.j. Doherty Ltd
Source: http://www.eplanning.ie/LouthCC/AppFileRefDetails/22984/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Louth County Council
- Application reference
- 22984
- Applicant
- P.j. & E.j. Doherty Ltd
- Agent
- P.j. & E.j. Doherty Ltd
- Decision stage
- Commencement
- Commenced
- 18 Oct 2024
- Units
- 1
- Floor area
- 58 m²
- Builder / developer
- P.j. & E.j. Doherty Ltd
Official description
Verbatim source text
Permission for a change of use of ancillary storage area at the former Amber Night Clubto facilitate the addition of 1no apartment, to the 5 no. previously granted under planning Ref No. 20/156. The building is a protected structure under the Louth County Development Plan 2015-2021 - Record of Protected Structure Ref No. D192, no alterations to the protected facade is envisioned.
Verify against official sourceExplore the area
More Louth planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- P.j. & E.j. Doherty Ltd
- Planning agent
- P.j. & E.j. Doherty Ltd
- Builder / developer
- P.j. & E.j. Doherty Ltd
Lifecycle timeline
Application to site progress
-
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Commenced
18 Oct 2024 Work started · A change of use of ancillary storage area -
Completed
Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Likely trades & supplier leads