Small residential · Co. Mayo

Erris street, crossmolina, Co. Mayo

Granted 16 Dec 2021 (final grant issued 28 Jan 2022)

We no longer update this application, so we can't email you about it. Get new planning applications in Crossmolina by email

Key facts

  • Planning application 211161 at Erris Street, Crossmolina, Co. Mayo: 2 homes.
  • It was received by Mayo County Council on 3 Nov 2021.
  • Status: Granted 16 Dec 2021 (final grant issued 28 Jan 2022).
  • Work was due to start on 31 May 2022, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Mayo County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Crossmolina · Planning applications in Co. Mayo

Council register

The council's register shows: Granted on 16 Dec 2021.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

2 homes

CONSTRUCTION OF A DWELLING HOUSE, DOMESTIC SHED, CONNECTION TO THE PUBLIC SERVICES ALONG WITH ANY SITE ANCILLARY WORKS

Location
Crossmolina, Co. Mayo Map
Planning reference
211161

Numbers and dates

Homes
2
Floor area
145 m²
Project type
Small residential
Received
3 Nov 2021
Decision to grant
16 Dec 2021
Final grant
28 Jan 2022
Site start notified
31 May 2022

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 31 May 2022, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 211161 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Mayo County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 31 May 2022Notice filed · Proposed dwelling houseView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Crossmolina

Get alerts for CrossmolinaFree. We email you when new applications appear.

Free email alerts

Get new Crossmolina projects by email

New applications, decisions and site starts in Crossmolina, Co. Mayo. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options