Site start · Co. Mayo

Ballina, Mayo

Granted 9 May 2023 (final grant issued 25 Jul 2024)

Key facts

  • Site start record 22531 at Ballina, Co. Mayo: Demolition of existing petrol filling station.
  • The planning authority is Mayo County Council.
  • Status: Granted 9 May 2023 (final grant issued 25 Jul 2024).

Source: the Mayo County Council planning register, as last seen on 12 Jul 2026. Open the council's file

More planning applications in Ballina · Planning applications in Co. Mayo

Council register

The council's register shows: Granted on 9 May 2023.

Application details as we last saw them in the national register on 12 Jul 2026.

What and where

Demolition of existing petrol filling station

DEMOLITION OF EXISTING PETROL FILLING STATION, CONVENIENCE SHOP AND ANCILLARY SITE FEATURES, CONSTRUCTION OF A PART TWO STOREY BUILDING (c.529 m²) COMPRISING OF RETAIL AREA WITH ANCILLARY OFF-LICENCE USE, ANCILLARY FOOD OFFER COUNTER, SEATING AREA, TOILETS, OFFICES AND ANCILLARY STORAGE AND FOOD PREPARATION AREAS, CONSTRUCTION OF A NEW FORECOURT WITH PUMP ISLANDS AND FORECOURT CANOPY, INSTALLATIONOF 2 NO. 40,000 L & 1 NO. 25,000L UNDERGROUND FUEL STORAGE TANKS, ASSOCIATED PIPEWORK AND ABOVE GROUND FILL POINTS, CONSTRUCTION OF ANCILLARY SINGLE STOREY STORAGE BUILDING (c. 55 m²), INSTALLATION OF A FREESTANDING ADVERTISING SIGN, CONSTRUCTION OF ALL ANCILLARY SITE FEATURES INCLUDING SCREENED STORAGE COMPOUND, SIGNAGE, BOUNDARY TREATMENTS, DRAINAGE SYSTEMS, LANDSCAPING, CAR PARKING AND ASSOCIATED SITE WORKS

Location
Ballina, Co. Mayo Map
Planning reference
22531
Application type
Commencement Notice
Owner named on the notice
Corrib Oil Company Limites
Agent named on the notice
P McHugh & Sons Ltd

Numbers and dates

Floor area
55 m²
Project type
Demolition
Received
29 Jun 2022
Decision to grant
9 May 2023
Final grant
25 Jul 2024
Site start notified
9 Jun 2025

Documents and evidence

Check the record

How we know this

From the Mayo County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 9 Jun 2025Notice filed · Construction of two storey convenience shop building and single storey ancillary storage...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Ballina

Get alerts for BallinaFree. We email you when new applications appear.

Free email alerts

Get new Ballina projects by email

New applications, decisions and site starts in Ballina, Co. Mayo. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.