37 dwellings, Crossmolina, Mayo - Planning Application 2460244

Mayo / Crossmolina / Crossmolina, Mayo

Est. value €3m–10m
Units 37
Floor area 4,204 m² (per planning documents)
Commenced 12 Dec 2024

Source-linked planning record

37 dwellings, Crossmolina, Mayo - Planning Application 2460244

Mayo / Crossmolina / Crossmolina, Mayo
PB ref
PB-332822
Plan ref
2460244
Authority
Mayo County Council
Stage / date
Commencement / 12 Dec 2024
Est. value band
€3m–10m
Units / floor
37 / 4,204 m² (per planning documents)
Project class
Large residential
Promoter
Craven Construcrtion Doonanarroo Ltd
Architect / agent
Craven Construcrtion Doonanarroo Ltd

Source: http://www.eplanning.ie/MayoCC/AppFileRefDetails/2460244/0

Key facts

Lead summary

Source
Owner-supplied commencement export
Planning authority
Mayo County Council
Application reference
2460244
Applicant
Craven Construcrtion Doonanarroo Ltd
Agent
Craven Construcrtion Doonanarroo Ltd
Decision stage
Commencement
Commenced
12 Dec 2024
Units
37
Floor area
4,204 m² (per planning documents)
Builder / developer
Craven Construcrtion Doonanarroo Ltd

Document insights

Extracted from official planning documents

Unit mix
10 2 bed semi-detached bungalow, 9 3 bed detached bungalow, 8 4 bed detached two story dwelling, 10 4 bed semi-detached two story dwelling
Floor area (per planning documents)
4,204 m²
Site area
2.938 ha
Scope
Development of 37 dwelling houses with associated site works and connections to public services.
Windows/doors: Sliding door, Wooden Ultra Tech Door, Fire escape windowsHeat pump: Air to Water Pump indicated in plant room

Facts only, extracted from official planning documents. Drawings and document packs are not republished.

source: Application Form - Part A, Mayo County Council planning file

Official description

Verbatim source text

The development will consist of 37 no. dwelling houses. Consisting of 10 no. 2 bed semi-detached bungalow, 9 no. 3 bed detached bungalow, 08 no. 4 bed detached two story dwelling & 10 no. 4 bed semi-detached two story dwelling. Also connected to public sewer/surface water & public water main. Including all other ancillary site work/services.

Verify against official source

Project team

Named source parties

Promoter
Craven Construcrtion Doonanarroo Ltd
Planning agent
Craven Construcrtion Doonanarroo Ltd
Builder / developer
Craven Construcrtion Doonanarroo Ltd

Lifecycle timeline

Application to site progress

  1. Applied

    26 Apr 2024 2460244
  2. Decision

    Conditional 23 Oct 2024
  3. Appeal

    No appeal indexed No public appeal record is indexed against this application.
  4. Commenced

    12 Dec 2024 Work started · phase 1 · Construction of 5 no. detached dwelling houses - Beech Hill, Mullenmore North...
  5. Commenced

    20 Dec 2024 Work started · phase 2 · Construction of 32 no. dwelling houses, a mix of detached & semi-detached, two story and...
  6. Completed

    Completion certificate recorded CC00000059729MO · recorded in Dec 2024 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 15 Sep 2026.
  7. Completed

    Completion certificate recorded CC00000059730MO · recorded in Dec 2024 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 15 Sep 2026.
  8. Completed

    Completion certificate recorded CC00000059734MO · recorded in Dec 2024 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 15 Sep 2026.

Likely trades & supplier leads

Inferred from scheme type and scale

ElectricalFire SafetyGroundworksHealth & SafetyMain contractorRoads/CivilsWindows/Doors