One-off house · Co. Mayo
Buncom, Ballyheane, Castlebar, Co. Mayo
Granted 1 May 2025 (final grant issued 2 Jun 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Castlebar by email
Key facts
- Planning application 2597 at Buncom, Ballyheane, Castlebar, Co. Mayo: Dwelling house.
- It was received by Mayo County Council on 12 Mar 2025.
- Status: Granted 1 May 2025 (final grant issued 2 Jun 2025).
- Work was due to start on 20 Jun 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Mayo County Council planning register, as last seen on 5 Oct 2026. Open the council's file
More planning applications in Castlebar · Planning applications in Co. Mayo
Council register
The council's register shows: Granted on 1 May 2025.
Search the Mayo planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Dwelling house
construction of a dwelling house, domestic garage, proprietary treatment unit and polishing filter and all ancillary site works
- Location
- Castlebar, Co. Mayo Map
- Council
- Mayo County Council
- Planning reference
- 2597
Numbers and dates
- Homes
- 1
- Floor area
- 220 m²
- Project type
- One-off house
- Received
- 12 Mar 2025
- Decision to grant
- 1 May 2025
- Final grant
- 2 Jun 2025
- Site start notified
- 20 Jun 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2597 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Mayo County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 20 Jun 2025Notice filed · Dwellinghouse at Buncom, BallyheaneView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.