Planning application · Co. Mayo

Townlands of Knockroe, Cunlaghfadda Harefield Cloonbaul and Knockaunakill, County Mayo.

Under appeal since 10 Aug 2026 (Refused 13 Jul 2026 by the council)

Get updates on this application

We'll email you if the decision is appealed and when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2660398 at Townlands of Knockroe, Cunlaghfadda Harefield Cloonbaul and Knockaunakill, County Mayo.: We, Cunlaghfadda Green Energy Limited.
  • The applicant is Cunlaghfadda Green Energy Ltd. The agent is Mike Amiel Mekell.
  • It was received by Mayo County Council on 20 May 2026.
  • Status: Under appeal since 10 Aug 2026 (Refused 13 Jul 2026 by the council).
  • The council's decision was appealed to An Coimisiún Pleanála. The appeal decides the outcome, and building work cannot start before it.

Source: the Mayo County Council planning register, checked 10 Aug 2026. Open the council's file

Planning applications in Co. Mayo

What and where

We, Cunlaghfadda Green Energy Limited

We, Cunlaghfadda Green Energy Limited, intend to apply for a ten-year planning permission for development in the townlands of Knockroe, Cunlaghfadda, Harefield, Cloonbaul and Knockaunakill, County Mayo. The development will comprise the provision of a renewable energy development consisting of the following: i. 7 no. wind turbines with a top of foundation to blade tip height of 160 metres; a rotor blade diameter of 136 metres; and hub height of 92 metres, 1 no. meteorological mast with a height of 92 metres and subsequent decommissioning of the wind turbines and meteorological mast following a thirty five-year operational life from the date of full commissioning of the wind turbines; ii. Turbine and meteorological mast foundations and associated temporary and permanent hard-standing areas; iii. All associated underground electrical and communications cabling and subsequent decommissioning of all underground cabling within the site connecting the turbines to a proposed 110kV substation following a thirty five year operational life from the date of full commissioning of the wind turbines; iv. 1 no. temporary construction compound; v. Upgrade and widening of existing internal tracks and provision of new permanent and temporary site access tracks and all associated site drainage; vi. Upgrade and temporary road widening works along the L15053 and provision of 1 no. passing bay; vii. 1 no. new temporary site entrance off the L1505 in the townland of Knockroe to accommodate the delivery of abnormal loads and construction phase traffic; viii. 1 no. new permanent site entrance in the townlands of Cunlaghfadda and Cloonbaul; ix. 1 no. borrow pit; x. 10 no. peat and spoil management areas; xi. 2 no. temporary security cabins; xii. Tree felling and vegetation removal; xiii. Biodiversity enhancement areas; xiv. Site drainage; xv. Site fencing, gates and signage; and xvi. All related site works above and below ground and all ancillary development.

Location
Co. Mayo Map
Planning reference
2660398

Numbers and dates

Received
20 May 2026
Council decision
13 Jul 2026
Appeal lodged
10 Aug 2026

Timeline

  1. Application received
  2. Refused by the council
  3. Appeal lodged

Outlook

What happens next

The council's decision was appealed to An Coimisiún Pleanála. The appeal decides the outcome, and building work cannot start before it.

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

Reviewed build intelligence

What the documents establish

Government document review

Pending appeal of the Mayo 2660398 wind-farm proposal. The retained council record reports refusal 13 July 2026; the inspected May 2026 EIAR describes a seven-turbine proposal and a separate grid-consent process, not approved or installed works.

2 official documents inspected · Checked 2026-09-05 · Official file index

Seven 160 m turbines;31.5 MW is an assessment assumption

Proposed in application · Mayo 2660398 wind-farm application; the separately consented grid connection is contextual

What the evidence says
The wind-farm application proposes seven turbines with 160 m tip height,92 m hub height and 136 m rotor diameter. The EIAR uses 4.5 MW per turbine to illustrate 31.5 MW, while expressly leaving generating capacity to the selected manufacturer. The separate 110 kV grid application is assessed in the same EIAR but follows a different consenting process.

Why it may matter — interpretation
Interpretation for turbine suppliers and planners: separates the proposed dimensional envelope from an assumed output and prevents shared EIAR content being mistaken for one permission.

What is not established
No turbine manufacturer, final generating capacity, permission, installed equipment or procurement status is established. The grid substation and off-site route are not added to the wind-farm consent.

Inspect the evidence

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.5
dual consenting process · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

dual consenting process

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.13
Rotor Diameter of 136 metres · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

Rotor Diameter of 136 metres

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.18
rated generating capacity of 4.5MW · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

rated generating capacity of 4.5MW

Reinforced-concrete foundations use an assessed 25 m envelope

Proposed in application · Proposed turbine gravity foundations; assessed envelope rather than an installed design

What the evidence says
The EIAR assesses foundations up to approximately 25 m horizontally and 3.5 m vertically, with an anchor cage and reinforcing steel. The embedded gravity-foundation drawing shows the 3.0–3.5 m foundation level separately from the deeper 4.0–4.5 m excavation. Final design depends on ground conditions and the turbine supplier.

Why it may matter — interpretation
Interpretation for concrete and groundworks specialists: distinguishes the foundation from its excavation and identifies the design dependency.

What is not established
No concrete volume, reinforcement tonnage, supplier or exact excavation at every turbine is established.

Inspect the evidence

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.15
approximately 25m and 3.5m · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

approximately 25m and 3.5m

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.16
4.0 - 4.5m · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

4.0 - 4.5m

The 20/33 kV detail shows 110 mm power ducts and 50 mm fibre ducting

Proposed in application · Internal turbine-to-substation cabling; typical on-track and off-track sections

What the evidence says
The proposed internal cable system uses 20/33 kV electricity and fibre communications. Figure 4-7 shows 110 mm power ducts with 12 mm draw ropes,50 mm solid-wall fibre ducting, a 600 mm trench width, yellow warning tape and Clause 804 backfill. The narrative allows the final duct number/configuration to change at detailed electrical design and requires clay plugs at intervals no greater than 50 m where needed.

Why it may matter — interpretation
Interpretation for electrical and civil trades: identifies ducting, backfill and runoff-barrier coordination while preserving the typical-section limitation.

What is not established
No route-wide duct quantity or final cable specification is established. The separate 110 kV export connection must not inherit this 20/33 kV section.

Inspect the evidence

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.19
not greater than 50 metres · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

not greater than 50 metres

Cunlaghfadda EIAR Chapter 4: Description, part 1 · p.21
110mm Diameter Ducts · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

110mm Diameter Ducts

Clean runoff uses level spreaders with site-dependent dimensions

Proposed in application · Drainage measures in the combined project EIAR; individual locations and lengths remain design-dependent

What the evidence says
The drainage strategy separates clean runoff from sediment-bearing construction water. Its level-spreader detail specifies a lip 150 mm above the ground behind it and a length between 4 m and 25 m, selected for the contributing catchment and ground conditions. The lip can be concrete kerb, timber board, pipe or a similar level-edged material.

Why it may matter — interpretation
Interpretation for drainage and landscaping trades: identifies a defined runoff-dissipation work with material alternatives.

What is not established
No number of spreaders, selected lip material, combined length or installed drainage system is established.

Inspect the evidence

Cunlaghfadda EIAR Chapter 4: Description, part 2 · p.20
Two distinct methods · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

Two distinct methods

Cunlaghfadda EIAR Chapter 4: Description, part 2 · p.23
minimum of four metres · Issued 2026-05-14 · Chapter 4 Final 2026.05.14; embedded engineering figures P01 dated 14 May 2026; received 2026-05-20 · Checked 2026-09-05

minimum of four metres
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 2 government-published PDFs were visually inspected. One hundred and seventeen Commission file links catalogued. Two PDFs comprising parts of the same EIAR chapter were accessed, with 11 selected pages visually inspected; the remaining document families and all pages were not exhaustively reviewed. Proposals do not establish procurement or installed work.

How we know this

From the Mayo County Council planning register, checked 10 Aug 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Co. Mayo

Get alerts for Co. MayoFree. We email you when new applications appear.

Free email alerts

Get new Mayo projects by email

New applications, decisions and site starts in Co. Mayo. Only when there is something new.