Commercial fit-out · Co. Meath
David Cullen House Kells Business Park, Cavan Road Kells, Co. Meath
Granted 23 Aug 2023 (final grant issued 3 Oct 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Meath by email
Key facts
- Planning application 2360156 at David Cullen House Kells Business Park, Cavan Road Kells, Co. Meath: Alterations to existing vacant industrial unit.
- It was received by Meath County Council on 11 Jul 2023.
- Status: Granted 23 Aug 2023 (final grant issued 3 Oct 2023).
Source: the Meath County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 23 Aug 2023.
Search the Meath planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Alterations to existing vacant industrial unit
(A) alterations to existing vacant industrial unit consisting of new milk testing laboratory on ground floor, toilets, staff area and passenger lift, (B) first floor offices, research laboratories and boardroom. (C) insertion of new window fenestration to all existing four elevations. (D) display signage on north elevation & east elevation.
- Location
- Cavan Road Kells, Co. Meath Map
- Council
- Meath County Council
- Planning reference
- 2360156
Numbers and dates
- Project type
- Commercial fit-out
- Received
- 11 Jul 2023
- Decision to grant
- 23 Aug 2023
- Final grant
- 3 Oct 2023
- Site start notified
- 10 Feb 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 2360156 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Meath County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 10 Feb 2025Notice filed · (A)Alterations to industrial unit consisting of laboratory on ground floor, toilets...View the site start
- Completion certificate recordedRecorded in Feb 2025 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.