Save this project to account
Back to leads
Commencement

110 dwellings, Navan, Meath - Planning Application 24201

Meath / Navan / Navan, Meath

Est. value €30m+
Units 110
Floor area 10,618 m²
Commenced 26 Nov 2025

Source-linked planning record

110 dwellings, Navan, Meath - Planning Application 24201

Meath / Navan / Navan, Meath
PB ref
PB-338306
Plan ref
24201
Authority
Meath County Council
Stage / date
Commencement / 26 Nov 2025
Est. value band
€30m+
Units / floor
110 / 10,618 m²
Project class
Planning record
Promoter
Cairn Homes Properties Ltd
Architect / agent
Cairn Homes Construction Ltd

Source: http://www.eplanning.ie/MeathCC/AppFileRefDetails/24201/0

Key facts

Lead summary

Source
Owner-supplied commencement export
Planning authority
Meath County Council
Application reference
24201
Applicant
Cairn Homes Properties Ltd
Agent
Cairn Homes Construction Ltd
Decision stage
Commencement
Commenced
26 Nov 2025
Units
110
Floor area
10,618 m²
Builder / developer
Cairn Homes Construction Ltd

Document insights

Extracted from official planning documents

Unit mix
2 2-bed house, 58 3-bed house, 4 4-bed house, 23 1-bed apartment, 23 2-bed apartment
Site area
3.43 ha
Applicant / promoter
Cairn Homes Properties Ltd
Phasing
Phase 3 of a larger residential development on the applicant's landholding, following Phase 1 (84 dwellings) and Phase 2 (48 dwellings) which are completed.
Scope
Construction of 110 residential units (64 houses and 46 apartments) with associated infrastructure, landscaping, and modifications to Phase 2 roads and parking.
Groundworks: Construction of internal roads, water supply, surface water and foul water drainage infrastructure including temporary foul water pumping stRainwater: Surface water drainage infrastructure.Wastewater: Foul water drainage infrastructure including temporary foul water pumping station.

Facts only, extracted from official planning documents. Drawings and document packs are not republished.

source: Planning Report & Statement of Consistency, Meath County Council planning file

Official description

Verbatim source text

Permission for a Large-Scale Residential Development - The application site comprises lands generally to the east and southeast of the recently constructed Swanbrook residential development (as permitted under ABP-311199-21 and MCC Reg. Ref. 221202 and amended by MCC Reg. Ref. 23403). The proposed development will consist of: 1. Construction of 110 no. new residential dwellings comprising 64 no. two storey houses (2 no. two-bed, 58 no. three-bed, and 4 no. four-bed, terraced and semi-detached houses) and 46 no. apartments (23 no. one-bed and 23 no. two-bed apartments) in a single four storey block with balconies on all of the elevations. 2. The proposed development will be accessed via permitted entrances (ABP Ref. ABP-311199-21 and MCC Reg. Ref. 221202, as amended by MCC Reg. Ref. 23403) and includes the continuation of the permitted North-South Link Street southwards by approximately 11Om. 3. A total of 184 no. car parking spaces (including 3 no. accessible spaces and 15 no. EV charging spaces), and 116 no. bicycle parking spaces (comprising 70 no. long term and 24 no. short term no. spaces serving the Apartment Block, and 22 no. additional short term spaces serving the wider scheme). 4. Modifications to development permitted under MCC Reg. Ref. 221202 (as amended by MCC Reg. Ref. 23403) to facilitate the extension of the permitted North-South Link Street; the incorporation of new junctions to serve the proposed development; and, the reconfiguration of the car parking layout serving the permitted childcare facility (MCC Reg. Ref. 23403) including the relocation of 4 no. spaces (no change to the permitted quantum of carparking serving the childcare facility is proposed). 5. Other associated infrastructure works including the provision of landscaped public and communal open spaces, bin storage, internal roads, boundary treatments, public lighting, ESB substation, water supply, surface water drainage and foul water drainage infrastructure (including a temporary foul water pumping station), and all associated and ancillary site and development works. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development. Significant further information/revised plans submitted on this application

Verify against official source

Project team

Named source parties

Promoter
Cairn Homes Properties Ltd
Planning agent
Cairn Homes Construction Ltd
Builder / developer
Cairn Homes Construction Ltd

Lifecycle timeline

Application to site progress

  1. Applied

    10 May 2024 24201
  2. Decision

    Conditional 8 Nov 2024
  3. Appeal

    No appeal indexed No public appeal record is indexed against this application.
  4. Commenced

    26 Nov 2025 Work started · Construction of 64 houses as permitted under Reg Ref 24/201 in Navan Co. Meath
  5. Completed

    Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.

Likely trades & supplier leads

Inferred from scheme type and scale

ComplianceElectricalFire SafetyHealth & SafetyPlanner/ConsultantSecuritySolar/Energy
Board this lead Create alert