Public / civic · Co. Meath
Dunshaughlin GAA Club, Drumree Road Dunshaughlin, Co. Meath A85CK22
Granted 22 Jul 2024 (final grant issued 5 Sep 2024)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Meath by email
Key facts
- Planning application 2460388 at Dunshaughlin GAA Club, Drumree Road Dunshaughlin, Co. Meath A85CK22: Temporary primary school building.
- It was received by Meath County Council on 28 May 2024.
- Status: Granted 22 Jul 2024 (final grant issued 5 Sep 2024).
Source: the Meath County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 22 Jul 2024.
Search the Meath planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Temporary primary school building
the development will consist of: The construction of a temporary primary school building, single storey with two classrooms, by way of construction of a prefabricated modular building with associated site works. Retention planning permission is also sought for two existing primary school modular buildings, single storey with two classrooms. Temporary Permission for a period no longer than 5 years is being sought
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Drumree Road Dunshaughlin, Co. Meath Map
- Council
- Meath County Council
- Planning reference
- 2460388
Numbers and dates
- Project type
- Public / civic
- Received
- 28 May 2024
- Decision to grant
- 22 Jul 2024
- Final grant
- 5 Sep 2024
- Site start notified
- 17 Sep 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 2460388 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Meath County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 17 Sep 2024Notice filed · phase 1 · This project involves the provision of temporary accommodation by way of construction of...View the site start
- 9 Jul 2025Notice filed · phase 2 · Temporary primary school building, single storey with two classrooms, by way of...View the site start
- Completion certificate recordedRecorded in Sep 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jul 2025 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.