Planning record · Co. Meath
PCI Pharma Services, Block 08 City North Business Campus, Stamullen Co. Meath K32 PX88
Granted 13 Mar 2025 (final grant issued 24 Apr 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Meath by email
Key facts
- Planning application 2560057 at PCI Pharma Services, Block 08 City North Business Campus, Stamullen Co. Meath K32 PX88: Development to be retained consist of as constructed modifications…
- It was received by Meath County Council on 20 Jan 2025.
- Status: Granted 13 Mar 2025 (final grant issued 24 Apr 2025).
Source: the Meath County Council planning register, as last seen on 5 Oct 2026. Open the council's file
Council register
The council's register shows: Granted on 13 Mar 2025.
Search the Meath planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Development to be retained consist of as constructed modifications…
the development to be retained consist of as constructed modifications to the permitted development comprising 1) revisions to permitted bike store to accommodate 98no. bicycle parking spaces, 2) minor revisions to elevations and external finishes of the building to include alteration of cladding profiles and adjustments to external fenestration and the dimensions and positions of loading bay doors and canopy, and 3) revisions to hard and soft landscaping elements. The proposed development will consist of both internal and external modifications to the permitted development comprising: 1) On the ground floor, the reconfiguration of the approved layout to allow for: a) the construction of a commercial-grade kitchen, staff canteen and associated store facilities, b) construction of a cold/freezer store, c) addition of GMP corridor, garbing and training areas, and engineering workshop, d) creation of new quality control inspection areas, e) new locker room and associated spaces, f) 2 no. production lines and area for future production line, and g) enclosed compactor area. 2) On the first floor, the reconfiguration of the approved layout to allow for: a) new administrative offices, meeting and training rooms, prayer room, and nursing room, b) a pallet gate and goods lift, c) construction of additional protected stairways and corridors, d) new open plan mezzanine, 4,360 m² in area, to provide for future production area, and e) new QC inspection office. 3) Externally, a) Installation of outdoor plant elements, including chillers and generators, and b) fire escape doors and stairways and corresponding pathways. The proposed development includes for the removal of condition No.5 of Reg. Ref. 23/60046 to better reflect to nature of the industrial warehousing and logistics/distribution use of the facility. All office space will remain ancillary to these uses. The proposed development also includes the omission of the permitted temporary wastewater treatment plant, which is now no longer required
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Co. Meath Map
- Council
- Meath County Council
- Planning reference
- 2560057
Numbers and dates
- Floor area
- 4,360 m²
- Project type
- Planning record
- Received
- 20 Jan 2025
- Decision to grant
- 13 Mar 2025
- Final grant
- 24 Apr 2025
- Site start notified
- 4 Jun 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 2560057 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Meath County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 4 Jun 2025Notice filed · The proposed development will consist of both internal and external modifications to the...View the site start
- Completion certificate recordedRecorded in Jun 2025 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.