Planning application · Co. Meath
Avourwen Platin Duleek Road, Lagavooren, Drogheda Co. Meath
Granted 30 Apr 2018 (final grant issued 14 Jun 2018)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Meath by email
Key facts
- Planning application LB180042 at Avourwen Platin Duleek Road, Lagavooren, Drogheda Co. Meath: 51 homes.
- It was received by Meath County Council on 19 Jan 2018.
- Status: Granted 30 Apr 2018 (final grant issued 14 Jun 2018).
Source: the Meath County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 30 Apr 2018.
Search the Meath planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
51 homes
construction of 3 no. 3 bed, 2 storey detached houses and 48 no. 3 bed, 2 storey semi detached houses together with landscaping, services and associated siteworks at The Cedars, The Pines and The Laurels, Avourwen, (Screening for Appropriate Assessment submitted). Previously, planning permission was granted for similar houses on the same site layout by way of Planning Register Reference Number SA/60309, subsequently extended by permission Planning Register Number SA/120088. Significant further information/revised plans submitted on this application
- Location
- Lagavooren, Co. Meath Map
- Council
- Meath County Council
- Planning reference
- LB180042
Numbers and dates
- Homes
- 51
- Floor area
- 6,630 m²
- Estimated construction value
- €10m to €13mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Received
- 19 Jan 2018
- Decision to grant
- 30 Apr 2018
- Final grant
- 14 Jun 2018
- Site start notified
- 26 Aug 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file LB180042 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Meath County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 26 Aug 2019Notice filed · phase 1 · Construction of units 30, 47-57 The Cedars, Avourwen, Platin, Duleek Rd, Drogheda Co.MeathView the site start
- 2 Dec 2019Notice filed · phase 2 · Construction of 1-25 The Pines & 19-32 The Laurels, Avourwen, Duleek Rd, Drogheda...View the site start
- Completion certificate recordedRecorded in Aug 2019 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Aug 2019 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Aug 2019 · 3 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area