- Planning application NA181168 at Unit 3-4 & Unit 5Navan Shopping Centre, Kennedy Road, Navan Co. Meath: Interconnection of Units 3-4 and Unit 5.
- It was received by Meath County Council on 5 Oct 2018.
- Status: Granted 27 Nov 2018 (final grant issued 17 Jan 2019).
Source: the Meath County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 27 Nov 2018.
Search the Meath planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Interconnection of Units 3-4 and Unit 5
(1) the interconnection of Units 3-4 and Unit 5, (2) the change of use in Unit 5 from retail use to pharmacy use (3) the removal of a mezzanine level within Unit 5 (4) the installation of signage to the shopfront internally within the mall and (5) all associated site works
- Location
- Co. Meath Map
- Council
- Meath County Council
- Planning reference
- NA181168
Numbers and dates
- Project type
- Commercial fit-out
- Received
- 5 Oct 2018
- Decision to grant
- 27 Nov 2018
- Final grant
- 17 Jan 2019
- Site start notified
- 6 Feb 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file NA181168 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Meath County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 6 Feb 2019Notice filed · The interconnection of Unit 3-4 & Unit 5, Navan Shopping Centre, Structural Works...View the site start
- Partial completion certificate recordedRecorded in Feb 2019 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in Feb 2019 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.