Planning application · Co. Meath
Athboy Road, Blackfriary, Trim Co. Meath
Granted 27 Jun 2018 (final grant issued 9 Aug 2018)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Meath by email
Key facts
- Planning application TA171223 at Athboy Road, Blackfriary, Trim Co. Meath: 26 no. 3-bed dwellings with optional rear annexe.
- It was received by Meath County Council on 20 Oct 2017.
- Status: Granted 27 Jun 2018 (final grant issued 9 Aug 2018).
Source: the Meath County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 27 Jun 2018.
Search the Meath planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
26 no. 3-bed dwellings with optional rear annexe
26 no. 3-bed dwellings with optional rear annexe and all associated site development works. Significant further information/revised plans submitted on this application
- Location
- Blackfriary, Co. Meath Map
- Council
- Meath County Council
- Planning reference
- TA171223
Numbers and dates
- Received
- 20 Oct 2017
- Decision to grant
- 27 Jun 2018
- Final grant
- 9 Aug 2018
- Site start notified
- 19 Feb 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file TA171223 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Meath County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 19 Feb 2019Notice filed · phase 1 · 20 No. 3-Bed Dwellings with Optional Rear Annex and 1 No. 4-Bed Detached Dwelling and...View the site start
- 3 Jun 2019Notice filed · phase 2 · 20 No. 3 Bed Dwellings with Optional Rear Annex and 1 No. 4 Bed Detached Dwelling and...View the site start
- Completion certificate recordedRecorded in Feb 2019 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jun 2019 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jun 2019 · 5 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.