One-off house · Co. Monaghan
Tedavnet, Co. Monaghan
Granted 29 Nov 2021 (final grant issued 10 Jan 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Tedavnet by email
Key facts
- Planning application 21452 at Tedavnet, Co. Monaghan: 12 semi-detached two storey houses.
- It was received by Monaghan County Council on 6 Aug 2021.
- Status: Granted 29 Nov 2021 (final grant issued 10 Jan 2022).
Source: the Monaghan County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Tedavnet · Planning applications in Co. Monaghan
Council register
The council's register shows: Granted on 29 Nov 2021.
Search the Monaghan planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
12 semi-detached two storey houses
permission for the construction of 12 semi-detached two storey houses, together with footpaths, roads, lighting, connection to public sewer, works to boundary and all associated site works
- Location
- Tedavnet, Co. Monaghan Map
- Council
- Monaghan County Council
- Planning reference
- 21452
Numbers and dates
- Homes
- 1
- Floor area
- 1,098 m²
- Project type
- One-off house
- Received
- 6 Aug 2021
- Decision to grant
- 29 Nov 2021
- Final grant
- 10 Jan 2022
- Site start notified
- 17 May 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 21452 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Monaghan County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 17 May 2022Notice filed · Construction of 12 semi-detached two-storey houses, together with footpaths, roads...View the site start
- Partial completion certificate recordedRecorded in May 2022 · 4 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in May 2022 · 4 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in May 2022 · 5 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.