Commercial new build · Co. Offaly

Axis business park, clara road ballyduff, tullamore Co. Offaly

Granted 26 Aug 2019 (final grant issued 3 Oct 2019)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Offaly by email

Key facts

  • Planning application 18541 at Axis Business Park, Clara Road Ballyduff, Tullamore Co. Offaly: 2 no. industrial/warehousing buildings and associated office…
  • It was received by Offaly County Council on 4 Dec 2018.
  • Status: Granted 26 Aug 2019 (final grant issued 3 Oct 2019).

Source: the Offaly County Council planning register, as last seen on 2 Jun 2026. Open the council's file

Planning applications in Co. Offaly

Council register

The council's register shows: Granted on 26 Aug 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

2 no. industrial/warehousing buildings and associated office…

2 NO. INDUSTRIAL/WAREHOUSING BUILDINGS AND ASSOCIATED OFFICE ACCOMMODATION, CAR-PARKING AND ALL ANCILLARY SITE WORKS

Location
Clara Road Ballyduff, Co. Offaly Map
Planning reference
18541

Numbers and dates

Project type
Commercial new build
Received
4 Dec 2018
Decision to grant
26 Aug 2019
Final grant
3 Oct 2019
Site start notified
2 Dec 2019

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file 18541 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Offaly County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 2 Dec 2019Notice filed · CONSTRUCTION OF 2 NO. INDUSTR IAL/WAREHOUSIN G BUILDINGS AND ASSOCIATED ACCOMMODATION...View the site start
  2. Completion certificate recordedRecorded in Dec 2019 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Clara Road Ballyduff

Get alerts for Co. OffalyFree. We email you when new applications appear.

Free email alerts

Get new Offaly projects by email

New applications, decisions and site starts in Co. Offaly. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options