Infrastructure · Co. Offaly

Townlands of Ballykilleen Ballinowlart North and Kilcumber, ., Co. Offaly

Decision to grant 24 Jun 2026

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2660152 at Townlands of Ballykilleen Ballinowlart North and Kilcumber, ., Co. Offaly: Period of 10 years for a grid connection for the previously approved.
  • The applicant is Kilcush Solar Farm Ltd. The agent is Caitriona Fox.
  • It was received by Offaly County Council on 20 Mar 2026.
  • Status: Decision to grant 24 Jun 2026.
  • The council decided on 24 Jun 2026 to grant permission. Final grant not yet recorded. No site start has been filed yet.

Source: the Offaly County Council planning register, checked 11 Jul 2026. Open the council's file

Planning applications in Co. Offaly

What and where

Period of 10 years for a grid connection for the previously approved

(RED III) a period of 10 years for a grid connection for the previously approved, but not yet constructed, solar energy development (Planning ref: 21/598). This will consist of installation of medium voltage (MV) electrical cabling between the solar arrays and the existing Philipstown 110kV substation, including a 8m section of cable within the R401 and a 56m section of overhead line and associated pole sets to facilitate crossing of the Figile River. A Natura Impact Statement (NIS) has been submitted as part of the application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413)

Location
Co. Offaly Map
Planning reference
2660152

Numbers and dates

Project type
Infrastructure
Received
20 Mar 2026
Decision to grant
24 Jun 2026Final grant not yet recorded

Timeline

  1. Application received
  2. Decision to grant

Site history

This site's history

  1. Earlier permission 21598 for this site: granted 19 Sep 2022.

    A PERIOD OF 10 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV DEVELOPMENT WITH A TOTAL SITE AREA OF CIRCA 117.47 HECTARES, TO INCLUDE PV PANELS… Named in this application's description

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

The council decided on 24 Jun 2026 to grant permission. Final grant not yet recorded. No site start has been filed yet.

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2660152 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Offaly County Council planning register, checked 11 Jul 2026. We link to the council's own file so you can check the official record before you act.

Explore the area

More planning activity near Co. Offaly

Get alerts for Co. OffalyFree. We email you when new applications appear.

Free email alerts

Get new Offaly projects by email

New applications, decisions and site starts in Co. Offaly. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options