Infrastructure · Co. Roscommon
Lissanisky Kilcash Moydow Moneymore Knockmeane and Skrine, County Roscommon.
Not yet validated by the council
Key facts
- Planning application 2660567 at Lissanisky Kilcash Moydow Moneymore Knockmeane and Skrine, County Roscommon.: Planning Application is subject to Section 34D of the Planning…
- The applicant is Natural Forces Renewable Energy Ltd.
- It was received by Roscommon County Council on 29 Oct 2026.
- Status: Not yet validated by the council.
- The council has not yet validated this application (checked that it is complete). Its decision date can change once it does.
Source: the Roscommon County Council planning register, checked 19 Nov 2026. Open the council's file
What and where
Planning Application is subject to Section 34D of the Planning…
The Planning Application is subject to Section 34D of the Planning and Development Act 2000 (as amended) and in accordance with Article 16(2) of the Renewable Energy Directive III (Directive 2023/2413) i.e. Completeness Check. Permission for development, which consists of an amendment to the previously consented development (Ref. 2360142 & ACP. PL20.319800): • The construction of one Enercon E138 Wind Energy Converter on a 99.79m tower with an electrical rating of 4.5MW and an overall tip height of 168.9m; • An amendment to substation design, changing from a block-built to a modular design comprising of 2 single-storey prefabricated modules surrounded by stock proof fencing; an ESB module measuring 14.33 m² and height of 3.41m and an IPP module measuring 33.31 m² and 3.89m in height; • An amendment to the statutory redline boundary to incorporate the following; • 20kV overhead line (OHL) and underground cable (UGC) between the permitted IPP substation and the point of connection to the national grid, comprising c.507m of OHL across private lands and c.985m of UGC within the L7135 and • All associated ancillary infrastructure and preparatory works such as the provision of the turbine delivery / haulage route, site access track and the provision of the new site entrance from the L7086. The operational lifespan of the development will be 35 years from the date of commercial operation. This planning application is subject to a Natura Impact Statement (NIS). This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application is subject to Section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with Section 34D(b), the provisions of Article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. This application is for a 10-year planning permission for a development with a total site area of 12.33 hectares, located in the townlands of
- Location
- Co. Roscommon Map
- Council
- Roscommon County Council
- Planning reference
- 2660567
- Application type
- Permission
- Applicant
- Natural Forces Renewable Energy Ltd
Numbers and dates
- Floor area
- 48 m²
- Project type
- Infrastructure
- Received
- 29 Oct 2026
Site history
This site's history
-
Earlier permission 2360142 for this site: decision to grant 3 May 2024.
Permission for a development relating to the: • The construction of one Enercon E138 Wind Turbine on an 81m tower with an electrical rating… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2660567 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Roscommon County Council planning register, checked 19 Nov 2026. We link to the council's own file so you can check the official record before you act.
Explore the area