Key facts
- Planning application 1822 at The Hilltop, Culleens, Co. Sligo: Retention and completion of development.
- It was received by Sligo County Council on 31 Jan 2018.
- Status: Granted 5 Sep 2018 (final grant issued 8 Oct 2018).
- Work was due to start on 24 Aug 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Sligo County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Culleens · Planning applications in Co. Sligo
Council register
The council's register shows: Granted on 5 Sep 2018.
Search the Sligo planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Retention and completion of development
permission for retention and completion of development consisting of (1) Ground floor shop (100sq.m) with storage area, office, solid fuel store and sanitary accommodation (First floor and basement are to be left as unused and inaccessible voids). (2) Service station with canopy over (3) 3 no. underground fuel storage tanks (2no. diesel tanks with capacity of 28,000 litres each and 1 no. petrol tank of 40,000 litres) and 1 no. surface diesel tank with capacity of 10,000 litres. (4) Car wash with water recycling unit. (5) Connect existing and proposed wastewater to new effluent treatment system. (6) Petrol interceptors. (7) Refuse storage compound. (8) Service area. (9) Car parking and truck parking to facilitate the development. (10) All associated signage. (11) Demolition of part of former dance hall and construction of new facade to same (floor area to be demolished is 53 sq.m). (12) Form 2 no. openings onto the N59 (1 for entrance only and 1 for entrance and exit) and associated turning lanes and road signage. (13) Retention of 2 no.s storage sheds in the south-east corner of the site (floor areas 366 sq.m and 145 sq.m) (14) Retention of 1no. storage container (floor area 33 sq.m) next to storage sheds. (15) Retention of 2.4m high wall behind commercial premises. (16) To carry out ancillary site works. The overall height of the development is 9.7m
- Location
- Culleens, Co. Sligo Map
- Council
- Sligo County Council
- Planning reference
- 1822
- Application type
- Retention permission
Numbers and dates
- Floor area
- 597 m²
- Project type
- Commercial fit-out
- Received
- 31 Jan 2018
- Decision to grant
- 5 Sep 2018
- Final grant
- 8 Oct 2018
- Site start notified
- 24 Aug 2020
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 1822 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Sligo County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 24 Aug 2020Notice filed · Retention and completion of Shop and Filling station, Culleens.View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.