Site start · Co. Sligo
Collooney, Sligo
Site start 23 Oct 2024
Archived record
This application has left our current planning lists, so this page is no longer updated. We last saw it in the council's register on 12 Jul 2026. The details below are as they were then. The council's register has the current status.
Search the Sligo planning registerCurrent planning applications in Collooney
What and where
Development will comprise the following
The development will comprise the following: a) Proposed extensions totalling circa. 595 m² to the existing Sligo Junction Filling Station consisting of additional seating, stores, food prep and sales areas, additional toilet facilities, staff welfare facilities and relocated drive thru hatch b) Change of Use of circa 30 m² of existing shop floor area to off - licence c) Revised internal layout of existing premises d) Proposed external self-service launderette machines. e) Relocation of car wash facility f) Small scale manufacturing facility circa 740 m² g) Construction of all ancillary site features including service yard, service connections, landscaping, EV charging substation, site layout alterations and parking. And associated site works
- Location
- Collooney, Co. Sligo Map
- Council
- Sligo County Council
- Planning reference
- 2360157
- Agent
- Sammon Developments Ltd
- Builder
- Sammon Developments Ltd
Key facts
- Floor area
- 30 m²
- Indicative value
- €250k–500kPlanningBrief estimate
- Project type
- Infrastructure
- Site start
- 23 Oct 2024
Documents and evidence
Check the record
- Council planning fileThe application file 2360157 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Sligo County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 23 Oct 2024Work started · A).Extension of existing Service Station B). Change of use shop floor C).Revised...
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.