Agricultural · Co. Sligo
Keenegahan, Ballymote, Co Sligo
Granted 17 Apr 2025 (final grant issued 20 May 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Ballymote by email
Key facts
- Planning application 2560049 at Keenegahan, Ballymote, Co Sligo: New slatted shed with loose area and feed passage.
- The agent is David Ross.
- It was received by Sligo County Council on 12 Feb 2025.
- Status: Granted 17 Apr 2025 (final grant issued 20 May 2025).
- Work was due to start on 20 Jun 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Sligo County Council planning register, as last seen on 5 Oct 2026. Open the council's file
More planning applications in Ballymote · Planning applications in Co. Sligo
Council register
The council's register shows: Granted on 17 Apr 2025.
Search the Sligo planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
New slatted shed with loose area and feed passage
(1) the construction of a new slatted shed with loose area and feed passage (2) the construction of a new dry shed and all associated site works, all at
- Location
- Ballymote, Co. Sligo Map
- Council
- Sligo County Council
- Planning reference
- 2560049
- Agent
- David Ross
Numbers and dates
- Project type
- Agricultural
- Received
- 12 Feb 2025
- Decision to grant
- 17 Apr 2025
- Final grant
- 20 May 2025
- Site start notified
- 20 Jun 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2560049 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Sligo County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 20 Jun 2025Notice filed · 2 new shedsView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area