Dunmore East, Waterford
Granted 19 May 2022 (final grant issued 14 Dec 2022)
Key facts
- Site start record 211133 at Dunmore East, Co. Waterford: 99 homes.
- The planning authority is Waterford City and County Council.
- Status: Granted 19 May 2022 (final grant issued 14 Dec 2022).
Source: the Waterford City and County Council planning register, as last seen on 12 Jul 2026. Open the council's file
More planning applications in Dunmore East · Planning applications in Co. Waterford
Council register
The council's register shows: Granted on 19 May 2022.
Search the Waterford planning register
Application details as we last saw them in the national register on 12 Jul 2026.
What and where
99 homes
Commencement Notice the construction of 99 no. dwelling (various types and sizes). The proposed development will include new vehicular and pedestrian access points at Killea Road, Archers Way and two new access points at Dunmore Holiday Villas, alterations to public footpath from the public roads at Killea Road, Archers Way and Dunmore Holiday Villas, 192 no private car parking spaces; 31 no. communal carparking spaces; 1.16 ha of public open space, foul and surface drainage including proposed wetlands attenuation pond; street lighting; landscaping; boundary treatments and all ancillary site development works necessary to facilitate the development
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Dunmore East, Co. Waterford Map
- Planning reference
- 211133
- Application type
- Commencement Notice
- Owner named on the notice
- S&k Carey Ltd
- Agent named on the notice
- S&k Carey Ltd
Numbers and dates
- Homes
- 99
- Floor area
- 15,036 m²
- Project type
- Large residential
- Received
- 7 Dec 2021
- Decision to grant
- 19 May 2022
- Final grant
- 14 Dec 2022
- Site start notified
- 1 May 2023
Documents and evidence
Check the record
- Council planning fileThe application file 211133 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealAppeal withdrawn · 313782 / 2 Dec 2022View the appeal record
How we know this
From the Waterford City and County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 1 May 2023Notice filed · phase 1 · Housing development at Killea, Dunmore East, Co. WaterfordView the site start
- 18 Apr 2024Notice filed · phase 2 · Housing development (72no units) at Killea, Dunmore EastView the site start
- 16 Dec 2024Notice filed · phase 3 · Housing development (9no units)View the site start
- Completion certificate recordedRecorded in May 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in May 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in May 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.