Large residential · Co. Westmeath
Jones Lake Road, Moate, Co Westmeath
Granted 3 Dec 2020 (final grant issued 6 Jan 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Moate by email
Key facts
- Planning application 207115 at Jones Lake Road, Moate, Co Westmeath: 35 homes.
- It was received by Westmeath County Council on 30 Jul 2020.
- Status: Granted 3 Dec 2020 (final grant issued 6 Jan 2021).
Source: the Westmeath County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Moate · Planning applications in Co. Westmeath
Council register
The council's register shows: Granted on 3 Dec 2020.
Search the Westmeath planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
35 homes
35 residential units including connection to existing services on the site together with car parking, landscaping and all associated site development works and services. The development will comprise 15 three-bedroom two-storey semi-detached units, 3 three-bedroom two-storey terraced units, 7 four-bedroom two-storey semi-detached units, 1 four-bedroom two-storey detached unit together with three blocks of two-storey plus attic duplex units each containing 1 two-bedroom two-storey semi-detached end unit, 1 two-bedroom ground floor apartment unit, 1 three-bedroom duplex unit on the first and second floor
- Location
- Moate, Co. Westmeath Map
- Council
- Westmeath County Council
- Planning reference
- 207115
Numbers and dates
- Homes
- 35
- Project type
- Large residential
- Received
- 30 Jul 2020
- Decision to grant
- 3 Dec 2020
- Final grant
- 6 Jan 2021
- Site start notified
- 31 Aug 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Appeal lodged
- Appeal decidedInvalid- late S.37(6)(a)
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 207115 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealInvalid- late S.37(6)(a) · 309136 / 11 Jan 2021View the appeal record
How we know this
From the Westmeath County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 31 Aug 2023Notice filed · phase 1 · Residential Development consisting of 17 no. houses as follows: Type A - 14 no. 3...View the site start
- 20 Feb 2024Notice filed · phase 2 · Residential Development consisting of 9 no. houses as follows: Type D - 3 no. 3 bedroom...View the site start
- 3 Oct 2024Notice filed · phase 3 · Development of a single apartment block comprising 3 units as follows: 2 bedroom end of...View the site start
- Completion certificate recordedRecorded in Aug 2023 · 3 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
- Completion certificate recordedRecorded in Aug 2023 · 3 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
- Completion certificate recordedRecorded in Aug 2023 · 11 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.