Temporary/event · Co. Wexford
Ballowen or Ramsfort Park, Gorey Rural, Co. Wexford
Granted 11 Jun 2021 (final grant issued 14 Jul 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Gorey by email
Key facts
- Planning application 20210614 at Ballowen Or Ramsfort Park, Gorey Rural, Co. Wexford: Development that will consist of the provision of a temporary.
- It was received by Wexford County Council on 26 Apr 2021.
- Status: Granted 11 Jun 2021 (final grant issued 14 Jul 2021).
Source: the Wexford County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Gorey · Planning applications in Co. Wexford
Council register
The council's register shows: Granted on 11 Jun 2021.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Development that will consist of the provision of a temporary
Permission for the development that will consist of the provision of a temporary
This description may be shortened. The full text is in the council's planning file.
- Location
- Gorey, Co. Wexford Map
- Council
- Wexford County Council
- Planning reference
- 20210614
Numbers and dates
- Project type
- Temporary/event
- Received
- 26 Apr 2021
- Decision to grant
- 11 Jun 2021
- Final grant
- 14 Jul 2021
- Site start notified
- 26 Oct 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 20210614 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Wexford County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 26 Oct 2021Notice filed · phase 1 · This project involves the provision of additional temporary post-primary school...View the site start
- 17 Dec 2021Notice filed · phase 2 · This project involves the provision of additional temporary post-primary school...View the site start
- 13 Apr 2022Notice filed · phase 3 · This project involves the provision of additional temporary post-primary school...View the site start
- 22 Apr 2025Notice filed · phase 4 · This project involves the provision of temporary accommodation by way of construction of...View the site start
- Partial completion certificate recordedRecorded in Oct 2021 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
- Partial completion certificate recordedRecorded in Dec 2021 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
- Partial completion certificate recordedRecorded in Apr 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.