  • Planning application 20220866 at Ballygillane Big, St Helen's, Co. Wexford: 27 homes.
  • It was received by Wexford County Council on 28 Jun 2022.
  • Status: Granted 26 Oct 2022 (final grant issued 28 Nov 2022).

Source: the Wexford County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in St Helen's · Planning applications in Co. Wexford

Council register

The council's register shows: Granted on 26 Oct 2022.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

27 homes

Permission for the construction of 27 no. fully serviced residential dwelling

Location
St Helen's, Co. Wexford Map
Planning reference
20220866

Numbers and dates

Homes
27
Estimated construction value
€3.9m to €5.9mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
28 Jun 2022
Decision to grant
26 Oct 2022
Final grant
28 Nov 2022
Site start notified
19 Mar 2024

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file 20220866 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Wexford County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 19 Mar 2024Notice filed · phase 1 · Construction of 8no. three bedroom dwellingsView the site start
  2. 6 Apr 2024Notice filed · phase 2 · Construction of 19no. 2 bed apartments and 1no. cafe/restaurant unit at Former Tuskar...View the site start
  3. Completion certificate recordedRecorded in Mar 2024 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near St Helen's

Get alerts for St Helen'sFree. We email you when new applications appear.

Free email alerts

Get new St Helen's projects by email

New applications, decisions and site starts in St Helen's, Co. Wexford. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options