One-off house · Co. Wexford

Killagoley, Enniscorthy Rural, Co. Wexford

Granted 24 Jul 2024 (final grant issued 26 Aug 2024)

We no longer update this application, so we can't email you about it. Get new planning applications in Enniscorthy by email

Key facts

  • Planning application 20231470 at Killagoley, Enniscorthy Rural, Co. Wexford: Serviced dwelling house with connections.
  • It was received by Wexford County Council on 7 Dec 2023.
  • Status: Granted 24 Jul 2024 (final grant issued 26 Aug 2024).
  • Work was due to start on 19 Aug 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Wexford County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Enniscorthy · Planning applications in Co. Wexford

Council register

The council's register shows: Granted on 24 Jul 2024.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Serviced dwelling house with connections

Permission to erect a serviced dwelling house with connections to

Location
Enniscorthy, Co. Wexford Map
Planning reference
20231470

Numbers and dates

Homes
~1estimated from the application
Project type
One-off house
Received
7 Dec 2023
Decision to grant
24 Jul 2024
Final grant
26 Aug 2024
Site start notified
19 Aug 2025

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Site history

This site's history

  1. Application 20211935E at the same address: received 12 Oct 2026, no decision recorded yet.

    Change of use of former psychiatric hospital grounds to residential use, demolition of disused agricultural shed and construction of 64 no… Same address

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work was due to start on 19 Aug 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 20231470 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Wexford County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 19 Aug 2025Notice filed · Proposed serviced dwelling house with connection to existing public services and carry...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Enniscorthy

Get alerts for EnniscorthyFree. We email you when new applications appear.

Free email alerts

Get new Enniscorthy projects by email

New applications, decisions and site starts in Enniscorthy, Co. Wexford. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options