One-off house · Co. Wexford
Cloonerane, Taghmon, Co. Wexford
Granted 12 Feb 2025 (final grant issued 18 Mar 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Taghmon by email
Key facts
- Planning application 20241063 at Cloonerane, Taghmon, Co. Wexford: Fully serviced dwelling and associated.
- It was received by Wexford County Council on 3 Sep 2024.
- Status: Granted 12 Feb 2025 (final grant issued 18 Mar 2025).
- Work was due to start on 4 Apr 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Wexford County Council planning register, as last seen on 5 Oct 2026. Open the council's file
More planning applications in Taghmon · Planning applications in Co. Wexford
Council register
The council's register shows: Granted on 12 Feb 2025.
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Fully serviced dwelling and associated
Permission for the erection of a fully serviced dwelling and associated
- Location
- Taghmon, Co. Wexford Map
- Council
- Wexford County Council
- Planning reference
- 20241063
Numbers and dates
- Homes
- 1
- Project type
- One-off house
- Received
- 3 Sep 2024
- Decision to grant
- 12 Feb 2025
- Final grant
- 18 Mar 2025
- Site start notified
- 4 Apr 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 20241063 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Wexford County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 4 Apr 2025Notice filed · Selb building 132sqm 3 bedroom bungalow Standard block built house with oil heating and...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.