  • Planning application 18745 at Ballinastoe, Roundwood, Co. Wicklow: New dwelling.
  • It was received by Wicklow County Council on 3 Jul 2018.
  • Status: Granted 19 Dec 2018 (final grant issued 31 Jan 2019).
  • Work was due to start on 10 Feb 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Wicklow County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Roundwood · Planning applications in Co. Wicklow

Council register

The council's register shows: Granted on 19 Dec 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New dwelling

new dwelling, well, effluent treatment & disposal system including replacement of existing vehicular entrance with a new vehicular entrance and ancillary works

Location
Roundwood, Co. Wicklow Map
Planning reference
18745

Numbers and dates

Homes
~1estimated from the application
Project type
One-off house
Received
3 Jul 2018
Decision to grant
19 Dec 2018
Final grant
31 Jan 2019
Site start notified
10 Feb 2020

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 10 Feb 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 18745 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Wicklow County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 10 Feb 2020Notice filed · New dwelling, well, effluent treatment & disposal system including replacement of...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Roundwood

Get alerts for RoundwoodFree. We email you when new applications appear.

Free email alerts

Get new Roundwood projects by email

New applications, decisions and site starts in Roundwood, Co. Wicklow. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options