Key facts
- Planning application 20192 at Back Street, Hudsons's Square, Abbeylands, Co. Wicklow: 7 homes.
- It was received by Wicklow County Council on 26 Feb 2020.
- Status: Granted 17 Jun 2020 (final grant issued 20 Jul 2020).
Source: the Wicklow County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 17 Jun 2020.
Search the Wicklow planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
7 homes
7 no units (7 no 2 bed houses) and all associated site works
- Location
- Abbeylands, Co. Wicklow Map
- Council
- Wicklow County Council
- Planning reference
- 20192
Numbers and dates
- Homes
- 7
- Floor area
- 700 m²
- Estimated construction value
- €1.0m to €1.4mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Small multi-unit
- Received
- 26 Feb 2020
- Decision to grant
- 17 Jun 2020
- Final grant
- 20 Jul 2020
- Site start notified
- 12 Jul 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 20192 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Wicklow County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 12 Jul 2021Notice filed · Construction of 7 no. 2 bed 2 storey terraced houses in one block and all associated...View the site start
- Completion certificate recordedRecorded in Jul 2021 · 7 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.